FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. Salesforce Certification
  3. Certified-Business-Analyst Exam
  4. Salesforce.Certified-Business-Analyst.v2024-02-19.q244 Dumps
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • …
  • »
  • »»
Download Now

Question 81

The business analyst (BA) at Northern Trail Outfitters is writing user stories for a Service Cloud implementation.
In which order should the BA arrange the three components of a user story?

Correct Answer: B
insert code

Question 82

Universal Containers is developing a new case management solution in Salesforce. The business analyst has started writing user stories to capture feature needs. One user story is: The customer care representative wants to take ownership of new cases and communicate with customers so they can provide high-touch customer experiences." Which component of the user story is "provide high-touch customer experiences?"

Correct Answer: C
insert code

Question 83

The scrum team working on Salesforce projects at Northern Trail Outfitters plans to review the current build with stakeholders to gather feedback. The business analyst will facilitate the meeting.
Which type of meeting should be held?

Correct Answer: C
Explanation
This answer selects sprint review as the type of meeting that should be held to review the current build with stakeholders and gather feedback. A sprint review is a meeting that takes place at the end of each sprint in the scrum methodology, where the development team demonstrates the working product increment to the stakeholders and collects their feedback. A sprint review helps to validate the requirements, evaluate the progress, and adjust the priorities for the next sprint.
References:https://trailhead.salesforce.com/en/content/learn/modules/agile-development-with-scrum/perform-a-s
insert code

Question 84

Universal Containers uses Kanban to complete its Salesforce development. In the middle of a sprint, the sales manager submits an important item to the team.
What should the business analyst do next?

Correct Answer: C
insert code

Question 85

Cloud Kicks is a rapidly growing company and has just expanded its team to include a business analyst (BA). The IT directory has asked the BA to use application Lifecycle Management (ALM) for all Salesforce development projects.
Which step of the ALM cycle requires the BA to study current business process gather requirements, and analyze them?

Correct Answer: C
insert code
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download Salesforce.Certified-Business-Analyst.v2024-02-19.q244 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.