How much of the Sprint Backlog must be defined during the Sprint Planning event?
To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, a Development Team to implement those ideas and a Scrum Master to help guide the process.
One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum?
(choose the best two answers)
Who owns the Sprint Backlog?