Explanation The Scrum Team consists of one Scrum Master, one Product Owner, and Developers. Within a Scrum Team, there are no sub-teams or hierarchies. It is a cohesive unit of professionals focused on one objective at a time, the Product Goal. The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide. They do this by helping everyone understand Scrum theory and practice, both within the Scrum Team and the organization. The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team. They are responsible for creating and communicating a vision, ordering the Product Backlog, and ensuring that the best possible job is done to delight customers. The Developers are the people in the Scrum Team that are committed to delivering a "Done" Increment that meets the Definition of Done and the Sprint Goal. They are responsible for managing and organizing their work within the Sprint, collaborating with the Product Owner and the Scrum Master, and applying their skills and creativity to create a product that delivers value to the stakeholders and customers. A Project Manager is not a role in the Scrum Team, as Scrum does not recognize titles for Developers, regardless of the work being performed by the person. There is no need for a Project Manager, as the Scrum Team is self-managing and accountable for delivering value. References: * The Scrum Guide * The Scrum Team * Professional Scrum Product Owner™ I Certification
Question 97
When is a Product Backlog item considered complete? (choose the best answer)
Correct Answer: C
The Definition of Done is a shared understanding of what it means for work to be complete, and ensures transparency of the quality of the work done1. A Product Backlog item is considered complete when it meets the Definition of Done, which means that it is usable and potentially releasable, and that it meets the quality standards set by the Scrum Team and the stakeholders2. The other options are not sufficient to determine the completeness of a Product Backlog item, as they may not reflect the actual value and quality of the product. References: 1: The Scrum Guide, November 2020, p. 13 2: The Scrum Guide, November 2020, p. 6
Question 98
Who is responsible to ensure, that stakeholders do not disrupt the Daily Scrum.
Correct Answer: A
Question 99
Which of the following are appropriate topics for discussion during a Sprint Retrospective? (choose the best two answers)
Correct Answer: A,C
Explanation The Sprint Retrospective is an event for the Scrum Team to inspect how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done1. The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness for the next Sprint2. Therefore, appropriate topics for discussion during a Sprint Retrospective are: Identifying high priority process improvements for the next Sprint. The Scrum Team should identify the most important things that went well and the potential improvements, and create a plan for implementing some of them in the next Sprint[3][3]. This way, the Scrum Team can continuously improve their performance and deliver more value. How the team collaborates. The Scrum Team should reflect on how they work together as a self-managing unit, and how they can enhance their skills, tools, and relationships4. This way, the Scrum Team can foster a culture of trust, respect, and collaboration. The other options are not appropriate topics for discussion during a Sprint Retrospective, as they are either related to the Product Backlog or the Sprint Backlog, which are not the focus of the Sprint Retrospective. The order of items in the Product Backlog is the responsibility of the Product Owner, who manages the Product Backlog based on the value, risk, and dependencies of the items5. The Product Owner may seek input from the Scrum Team or the stakeholders, but the final decision is up to the Product Owner. Documenting acceptance criteria for items in the next Sprint is part of the Product Backlog refinement, which is an ongoing activity throughout the Sprint, not a specific event. The Scrum Team should collaborate on refining the Product Backlog items and adding more details, such as acceptance criteria, as they become more clear and ready for selection in a Sprint Planning. References: 1: The Scrum Guide, November 2020, p. 14 2: The Scrum Guide, November 2020, p. 15 [3][3]: The Scrum Guide, November 2020, p. 15 4: Developing People and Teams, Scrum.org, accessed on December 16, 2023 5: The Scrum Guide, November 2020, p. 7 The Scrum Guide, November 2020, p. 10 The Scrum Guide, November 2020, p. 10 Understanding and Applying the Scrum Framework, Scrum.org, accessed on December 16, 2023
Question 100
Who is responsible for the sizing of Product Backlog items? (choose the best answer)
Correct Answer: D
According to Scrum.org, the Developers who will be doing the work are responsible for the sizing of Product Backlog items1. The Product Owner may influence the Developers by helping them understand and select trade-offs1. This implies that the Developers size the items after clarifying requirements with the Product Owner1.