FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. Scrum Certification
  3. PSPO-I Exam
  4. Scrum.PSPO-I.v2026-10-15.q144 Dumps
  • ««
  • «
  • …
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
Download Now

Question 141

As a Product Owner, which of the following tasks should you do?

Correct Answer: B,C
insert code

Question 142

Items in the Sprint still not meet the Definition of Done .
What should you do as a Scrum Team?

Correct Answer: B
insert code

Question 143

What should the Scrum Team do during the first Sprint?
(Choose the best answer)

Correct Answer: C
The correct answer isC.
The purpose of every Sprint, including the first Sprint, is to create a valuable, useful Increment. Scrum is based on empiricism, meaning teams learn through doing, inspecting results, and adapting. Therefore, the first Sprint should produce something tangible and valuable rather than focusing only on long-term planning or documentation.
Why the other options are incorrect:
A). Make up a plan for the rest of the project- Scrum does not require full up-front planning for the whole project. Plans emerge and adapt over time.
B). Define the major product features and a release plan architecture- this may happen in some organizations, but it is not the main purpose of the first Sprint.
D). Analyze, describe, and document the requirements for the subsequent Sprints- Scrum is not a phase- based requirements process. The goal is to deliver value each Sprint.
insert code

Question 144

True or False: Dependencies could influence how the Product Owner orders Product Backlog items.

Correct Answer: A
Dependencies are relationships between Product Backlog items that affect their order of implementation. For example, a Product Backlog item may depend on another one to be completed first, or it may have a dependency on a third-party system or resource. Dependencies could influence how the Product Owner orders Product Backlogitems, as they may introduce risks, constraints, or uncertainties that affect the value delivery.
The Product Owner should try to minimize dependencies and order the Product Backlog items in a way that maximizes value and minimizes waste.
[Professional Scrum Product Owner], chapter 6: "Dependencies are relationships between Product Backlog items that affect their order of implementation."
[Managing Dependencies on Agile Projects]: "Dependencies can have a significant impact on the delivery of value."
insert code
  • ««
  • «
  • …
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
[×]

Download PDF File

Enter your email address to download Scrum.PSPO-I.v2026-10-15.q144 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.