Much evidence is available that this ideal information system integration is not evolving within industry supply chains, since:
The quantity on hand plus the quantity ordered must equal the sum of the demand during the lead time plus the demand during the review period plus safety stock.
Planned input 30 30 20 20 20 20
Planned output 20 20 20 20 20 20
Planned backlog
Actual backlog 50
The planned backlog at the end of period 6 is?