What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?
Correct Answer: A
Arrow Diagramming Method (ADM): * Also known as Activity-on-Arrow (AoA). * Activities are represented as arrows, and only finish-to-start (FS) relationships are supported. * ADM has limitations in representing other relationships like start-to-start (SS), finish-to-finish (FF), or start-to-finish (SF). Precedence Diagramming Method (PDM): * Known as Activity-on-Node (AoN). * Activities are represented as nodes (boxes), allowing for flexibility in logic relationships, including FS, SS, FF, and SF. PSP Study Guide References: * The PSP Study Guide highlights that PDM has more advanced capabilities compared to ADM, particularly in defining diverse logical relationships. Conclusion: The correct answer is A, as ADM is restricted to finish-to-start logic, while PDM offers more flexibility.
Question 17
Which of eth following is NOT the type of insurance?
Correct Answer: D
Question 18
What not only reflect an applicant's financial situation and stability, they also provide other useful solution such as past addresses and previous employers?
Correct Answer: B
Question 19
Should activities be coded with the EBS value?
Correct Answer: D
Question 20
Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?