To deal with the lack of security, both government organizations have developed guidelines for protecting electric facilities and distribution systems. On the private side, the Edison Electric Institute developed guidelines that have been passed on to the North American Electric Reliability Council (NERC), the U.S.
Department of Energy's coordinator for the U.S. electrical infrastructure. Among other things the guide lines cover:
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?