Prior to circulating the service specification to a tendering supplier, it is good practice for the purchasing organisation to request completion of a non-disclosure agreement. Is this statement correct?
Correct Answer: B
Non-disclosure agreements (NDAs) are legally binding documents that protect confidential and proprietary information, including intellectual property, during pre-contractual discussions. NDAs ensure that sensitive data shared during early engagement or tender development is not misused. Reference:CIPS L4M3 Commercial Contracting Study Guide, Chapter 3, Section 3.2.1 - Confidentiality agreements and intellectual property protection.
Question 112
Which of the following best defines an 'express' term in general contract arrangements?
Correct Answer: D
Express terms are the terms of the agreement which are expressly agreed between the parties. Ideally, they will be written down in a contract between the parties but where the contract is agreed verbally, they will be the terms discussed and agreed between the parties. Implied terms are terms implied into the contract by the courts. They are not expressly set out in the contract but are taken to be as effective as if they were and as if they had been included from day one of the contract. The express terms and any implied terms together create the legally binding obligations on the parties. Reference: - Contracts: Express and Implied Terms - CIPS study guide 126-132 LO 3, AC 3.1
Question 113
When a supplier signs an insurance policy with an insurance company, which of the following is transferred to insurance company?
Correct Answer: B
An insurance policy transfers a specific set of risks such as the fire and flood risk for a particular asset. The legal liability does not transfer to the insurance company (known as insurer). Reference: CIPS study guide page 150 LO 3, AC 3.2
Question 114
GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days. Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts. Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?
Correct Answer: D
A liquidated damages clause specifies a predetermined amount of money that must be paid as damages for failure to perform under a contract. The amount of the liquidated damages is supposed to be the parties' best estimate at the time they sign the contract of the damages that would be caused by a breach. If a breach occurs and the liquidated damages clause is enforceable, the parties do not calculate the actual damages (i.e., how much money a party actually lost as a result of the breach). Instead, the breaching party pays the predetermined sum provided by the liquidated damages provision. To be enforceable, a liquidated damages clause should meet the following criteria. Damages are difficult to estimate. A court will be more likely to enforce a liquidated damages provision if the damages that will be incurred as a result of a breach of the contract are difficult to estimate when the contract is entered into. In certain situations, injuries are easy to prove. For example, if a breach will result in the loss of sales, it is easy to determine the actual damages by calculating lost profits. Others are more difficult, like the harm caused by breach of a confidentiality agreement or theft of trade secrets. To be enforceable, the damages should be either uncertain or difficult to quantify at the time the contract is entered into. The amount is reasonable and not a penalty. If the amount of the liquidated damages is grossly disproportionate to the actual harm incurred, a court will likely find it is a penalty or punishment and will not enforce the provision. When making this analysis, courts usually consider what was reasonable at the time the contract was entered into as opposed to when the breach occurred. There have been cases, however, where courts will decide the reasonableness of the damage estimate based on the actual harm at the time of the breach. The scenario is excerpted and edited based on a real world case law. In that case, the court held that GPP was entitled to liquidated damages under all four of the EPC contracts, ruling that the provisions did not amount to unenforceable penalties in each of the contracts. Reference: - CIPS study guide page 158-159 - Liquidated damages in energy projects - What Is a Liquidated Damages Provision? LO 3, AC 3.2
Question 115
Which of the following is the model form of contract for construction which is recommended by World Bank?
Correct Answer: D
FIDIC is the International Federation of Consulting Engineers (or Federation Internationale des Ingenieurs Conseils in French). FIDIC has produced many publications, including the model form contracts, best practice guidances, research on sustainability, integrity and risk management. FIDIC model form contracts have been developed by this organisation since 1999, now they consist of several different books which are marked by colours. Thus, FIDIC model contracts also have the nickname "Rainbow suite of contracts". Basically, the "Rainbow Suite" include the following books: * Yellow book: Plant and Design-Build Contract (2 editions: 1999 and 2017) * Silver book: EPC/Turnkey Contract (2 editions: 1999 and 2017) * Red book: Construction Contracts (2 editions: 1999 and 2017) * Emerald book: Conditions of Contract for Underground Works (1st Ed 2019) * Blue-Green book: Dredgers Contract (2 editions: 2006 and 2016) * Gold book: Design, Build and Operate Contract Guide * Pink book: Construction Contract Multilateral Development Bank Harmonised Ed (2 editions: 2005 and 2010) This type of model contract is commonly used around the world because its author, International Federation of Consulting Engineers, collaborates closely with development banks such as World Bank, Africa Development Bank, Asia Development Bank, etc. Every construction project that is financed by these institutions must adopt the FIDIC contracts. The Joint Contracts Tribunal, also known as the JCT, produces standard forms of contract for construction, guidance notes and other standard documentation for use in the construction industry in the United Kingdom. From its establishment in 1931, JCT has expanded the number of contributing organisations. ITC (International Trade Centre) produces contracts specifically designed for small companies doing international business, covering the sale of goods, distribution, services and joint ventures. Many small companies are now engaged in international trade, but don't have access to the necessary contract forms to protect themselves. ITC and leading legal experts developed eight generic contract templates that incorporate internationally recognized standards and laws for most small business situations. CIPS has several model forms of contract designed specifically for IT buying and servicing. Reference: LO 3, AC 3.1