FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. CompTIA Certification
  3. PK0-005 Exam
  4. CompTIA.PK0-005.v2026-01-27.q102 Dumps
  • ««
  • «
  • …
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • …
  • »
  • »»
Download Now

Question 71

A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?

Correct Answer: A
Explanation
The project manager should use a Pareto chart to prioritize which defects to address for the product. A Pareto chart is a type of bar chart that shows the frequency or impact of different causes of problems or defects. It also shows a cumulative line that represents the percentage of the total frequency or impact. A Pareto chart can help to prioritize the causes that have the most significant effect on the quality of the product and apply the
80/20 rule, which states that 80% of the problems are caused by 20% of the causes.
insert code

Question 72

Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?

Correct Answer: D
PaaS (Platform as a Service) provides a platform allowing developers to build and deploy applications quickly. It offers development tools and integrations with the operating system, which speeds up development and delivery. This model is highlighted in CompTIA Project+ as ideal for software development environments.
insert code

Question 73

Which of the following is a typical characteristic of Scrum?

Correct Answer: C
A self-organized team is a typical characteristic of Scrum, which is an agile framework for managing complex
projects. A self-organized team is a group of motivated and skilled individuals who have the autonomy and
authority to make decisions and collaborate on how to deliver the project goals. A self-organized team does
not rely on a manager or a leader to assign tasks, monitor progress, or resolve issues. Instead, a self-organized
team uses Scrum events, such as daily stand-ups, sprint planning, sprint review, and sprint retrospective, to
coordinate their work, communicate with each other, and inspect and adapt their process and product123.
References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 2: Project
Methodologies, p. 55; Scrum Characteristics - Scrumversity; What is Scrum? | Scrum.org; Characteristics of a
Great Scrum Team | Scrum.org
insert code

Question 74

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

Correct Answer: D
Adding contingency buffers to the critical path is a method to account for potential delays, increasing project certainty. This technique is part of risk management and schedule management, as recommended by CompTIA Project+.
insert code

Question 75

SIMULATION
During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.
INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in the following order:
1. Select the best tool for tracking the server migration progress.
2. Select the new critical path.
3. Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Select the Appropriate Tool:





Select the new critical path.
Option A

Option B

Option C

Correct Answer:
See the solution below in explanation
Explanation:
insert code
  • ««
  • «
  • …
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download CompTIA.PK0-005.v2026-01-27.q102 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.