You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating a meeting invite for the Sprint Review to demo the items completed in the Sprint. Who should you invite as a required attendee to the Sprint Review?
1. Product Owner(s)
2. Development Team
3. Business Users
Which of the following are scrum challenges to a team, organizations or an individual? (Choose three.)
As the Sprint planning progresses, the workload has grown beyond the development team's capacity.
Which action makes most sense for the Team?
During the sprint review the project is assessed against the ____________