Which of the following must be in existence as a precondition to developing an effective system of internal controls?
An audit identified a number of weaknesses in the configuration of a critical client/server system. Although some of the weaknesses were corrected prior to the issuance of the audit report, correction of the rest will require between 6 and 18 months for completion. Consequently, management has developed a detailed action plan, with anticipated completion dates, for addressing the weaknesses. What is the most appropriate course of action for the chief audit executive to take?
When creating the internal audit plan, the chief audit executive should prioritize engagements based primarily on which of the following?
Which of the following stages of contracting focuses on aligning the markets with objectives of the organization?