A business analyst (BA) wants to estimate the potential value delivered by a set of requirements and design options by targeting a small group of stakeholders to understand their perceived value and expectations. The BA is going to organize a discussion during which feedback is collected.
Which technique will be used?
A popular department store chain wants to make computer upgrades as well as conduct a major remodeling effort to increase revenue to all their 100 stores over the next 2 years. The remodeling will occur in two phases.
The two phases are required at each store and can be completed in any order, but each phase must be fully completed before the next phase can begin. Phase 1 will take approximately 32 weeks and will not require a store to be temporarily closed. Phase 2 will take approximately 20 weeks and will require a store to be temporarily closed.
In order to keep inventory level and total revenue for the department store chain at an operational level, 75% of the stores must remain open to the public at all times. Against the board of director's advice, the Chief Executive Officer (CEO) made a decision to start and complete the top 25 revenue-producing stores in the first year to get those stores remodeled and fully operational.
A business analyst (BA) has been brought in to help with planning the project and gathering requirements.
What activity should the BA do to determine which stores will be the first to start the renovations?
A business analyst (BA) wants to estimate the potential value delivered by a set of requirements and design options by targeting a small group of stakeholders to understand their perceived value and expectations. The BA is going to organize a discussion during which feedback is collected.
Which technique will be used?
Which of the following terms is used to describe a major deliverable or key even in the project used to measure project progress?
Some of the requirements in the solution must be completed because of laws and regulations in your industry. Management would like you, the business analyst, to rank the requirements according to the relevant laws. What type of requirements prioritization is management having you complete?