You are the business analyst for a new project. Part of this project is for the project team to manually install new workstations through the company's campus. Based on your research you have determined that the project team can install 25 new workstations per hour. Since there is a fixed amount of time that these workstations need to be installed you are considering adding additional labor for the implementation. You are also considering to adjust the prioritization of the project requirements based on the amount of workstations the project team can install per hour.
What does the 25 workstations per hour represent in this scenario?
You are the business analyst for your organization. You are currently working with Steve on the organize requirements process. You and Steve have elected to use the user stories approach for this process. What is the user stories approach for requirements organization?
Which of the following tasks cannot start until other tasks are completed?
Which one of the following diagrams when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work?
Holly is the business analyst for her organization. Holly encourages teamwork and open communications among the business analysis team and the stakeholders. She wants stakeholders to drop by her office and freely discuss the requirements, the solution scope, and other concerns about the solution she's working on.
Holly definitely prefers informal communications.
What is the danger Holly may experience with informal communications?