Which of the following would BEST enable business innovation through IT?
Correct Answer: C
Question 132
An enterprise plans to migrate its applications and data to an external cloud environment. Which of the following should be the ClO's PRIMARY focus before the migration?
Correct Answer: A
Reviewing the information governance framework should be the CIO's primary focus before the migration, because it will help the CIO to ensure that the enterprise's data and applications are secure, compliant, and aligned with the business objectives and policies in the cloud environment. The information governance framework defines the roles, responsibilities, processes, standards, and metrics for managing information assets across the enterprise. It also covers aspects such as data classification, data quality, data protection, data retention, data sovereignty, and data privacy. By reviewing the information governance framework, the CIO can identify the requirements, risks, and gaps that need to be addressed before moving to the cloud. The other options are not as important as reviewing the information governance framework, because they are either dependent on or secondary to it. Selecting best-of-breed cloud offerings is a tactical decision that should be based on the information governance framework and the enterprise architecture. Updating the enterprise architecture repository is a good practice, but not a primary focus before the migration. It can be done after the migration to reflect the changes in the IT landscape. Conducting IT staff training to manage cloud workloads is a necessary step, but not a primary focus before the migration. It can be done in parallel with or after the migration to ensure that the IT staff have the skills and knowledge to operate and optimize the cloud environment. References := Migration environment planning checklist, Practical Guide to Cloud Governance, Governance or compliance strategy
Question 133
DRAG DROP Drag and drop the various SSE-CMM levels at the appropriate places.
Correct Answer:
Question 134
The MOST effective way to ensure that IT supports the agile needs of an enterprise is to:
Correct Answer: C
The MOST effective way to ensure that IT supports the agile needs of an enterprise is to develop a robust enterprise architecture (EA). Enterprise architecture is the practice that supports organizations to understand the complexity of their own business components so they can be changed in a consistent way1. Enterprise architecture provides a framework for change, linked to both strategic direction and business value. It provides organization views to manage complexity, support continuous change, and keep the adequate level of balance between risk and innovation1. Enterprise architecture is also key to support strategic decision making, to provide guidance and guardrails to IT teams that are focused on agile delivery solutions2. Some of the benefits of developing a robust enterprise architecture for an agile enterprise are3: * It aligns the IT objectives and activities with the business strategy and expectations * It enables faster and more effective delivery of IT solutions that meet customer needs and expectations * It reduces waste, duplication, and technical debt by promoting reuse, standardization, and integration of IT assets * It fosters innovation and experimentation by providing a clear vision, direction, and roadmap for new and emerging technologies * It enhances collaboration and communication among stakeholders by providing a common language and understanding of the organization's architecture Therefore, developing a robust enterprise architecture is the most effective way to ensure that IT supports the agile needs of an enterprise.
Question 135
Jane is the project manager of the GBB project for her company. In the current project a vendor has offered the project a ten percent discount based if they will order 100 units for the project. It is possible that the GBB Project may need the 100 units, but the cost of the units is not a top priority for the project. Jane documents the offer and tells the vendor that they will keep the offer in mind and continue with the project as planned. What risk response has been given in this project?