FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CISA Exam
  4. ISACA.CISA.v2023-03-04.q546 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 1

Company.com has contracted with an external consulting firm to implement a commercial financial system to replace its existing in-house developed system. In reviewing the proposed development approach, which of the following would be of GREATEST concern?

Correct Answer: B
A quality plan is an essential element of all projects. It is critical that the contracted supplier be required to produce such a plan. The quality plan for the proposed development contract should be comprehensive and encompass all phases of the development and include which business functions will be included and when. Acceptance is normally managed by the user area, since they must be satisfied that the new system will meet their requirements. If the system is large, a phased-in approach to implementing the application is a reasonable approach. Prototyping is a valid method of ensuring that the system will meet business requirements.
insert code

Question 2

Which procedure provides the GREATEST assurance that corrective action to an audit report has been taken?

Correct Answer: B
insert code

Question 3

During an audit of a mission-critical system hosted in an outsourced data center, an IS auditor discovers that contracted routine maintenance for the alternate power generator was not performed. Which of the following should be the auditor's MAIN concern?

Correct Answer: B
Section: The process of Auditing Information System
insert code

Question 4

An IS auditor is assigned to perform a postimplementation review of an application system. Which of the following situations may have impaired the independence of the IS auditor? The IS auditor:

Correct Answer: A
Independence may be impaired if an IS auditor is, or has been, actively involved in the development, acquisition and implementation of the application system. Choices B and C are situations that do not impair an IS auditor's independence. Choice D isincorrect because an IS auditor's independence is not impaired by providing advice on known best practices.
insert code

Question 5

During an IS audit the auditor identifies significant delays in granting computer access to new employees. Which of the following should be reviewed FIRST to determine the root cause?

Correct Answer: A
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CISA.v2023-03-04.q546 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.