Which of the following is the PRIMARY purpose of implementing an enterprise governance of information and technology (EGIT) system?
Correct Answer: C
Question 67
Which of the following is ESSENTIAL to help ensure that a project's benefits are identified and continually monitored?
Correct Answer: A
A well-developed business case is essential to help ensure that a project's benefits are identified and continually monitored. A business case is a document that provides the rationale and evidence for initiating, continuing, or terminating a project or program. A business case typically consists of several elements, such as problem statement, objectives, scope, benefits, costs, risks, assumptions, etc. A well-developed business case helps to ensure that a project's benefits are identified and continually monitored by defining the expected outcomes or value that will be delivered by the project, as well as the metrics and indicators that will be used to measure and track them.12 References: COBIT 2019 Framework: Introduction and Methodology, COBIT 2019 Implementation Guide: Implementing an Information and Technology Governance Solution
Question 68
When tailoring the COBIT organization structure to organizational context and priorities, which of the following should be done NEXT after mapping organizational structures with specific responsibility or accountability?
Correct Answer: B
Question 69
Which of the following BEST enables an enterprise to show and prove the benefits realized from the implementation of an EGIT program plan?
Correct Answer: D
Explanation The best way to enable an enterprise to show and prove the benefits realized from the implementation of an EGIT program plan is to communicate the results and benefits in business impact terms. The EGIT program plan is a document that describes the rationale, objectives, scope, approach, benefits, costs, risks, and timeline of the EGIT implementation program. The EGIT implementation program is a program that involves designing and implementing a governance system for an enterprise using COBIT 2019. Communicating the results and benefits in business impact terms means using appropriate tools, methods, formats, frequencies, etc., to report on the progress and outcomes of the EGIT implementation program to relevant stakeholders such as the board, executives, business managers, IT managers, etc., using language and metrics that demonstrate how the program has contributed to achieving the enterprise's strategy, objectives, performance, value, etc. By communicating the results and benefits in business impact terms, an enterprise can ensure that it has a clear and compelling evidence of the value and benefits delivered by the EGIT implementation program, that it has met stakeholder requirements and expectations, that it has obtained stakeholder feedback and recognition, that it has enhanced stakeholder trust and confidence, etc12 References: 1: COBIT 2019 Implementation Guide: page 51-52 2: COBIT 2019 Framework: Governance and Management Objectives: page 19-20
Question 70
Which governance component identifies the human resource needs that must be met to achieve governance and management objectives?
Correct Answer: B
Explanation The people, skills and competencies component of governance identifies the human resource needs that must be met to achieve governance and management objectives. People are the individuals or groups who perform or are accountable for the governance activities and tasks. Skills and competencies are the abilities and knowledge that people need to perform their roles and responsibilities. The people, skills and competencies component of governance defines the required roles and organizational structures for each governance and management objective, as well as the skills and competencies that are needed for each role.13 References: COBIT 2019 Framework: Introduction and Methodology, COBIT 2019 Framework: Roles, Responsibilities & RACI Charts