FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2022-10-16.q179 Dumps
  • ««
  • «
  • …
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • …
  • »
  • »»
Download Now

Question 41

You are working in an enterprise. You enterprise is willing to accept a certain amount of risk. What is this risk called?

Correct Answer: C
Explanation/Reference:
Explanation:
Risk appetite considers the qualitative and quantitative aspects of accepting risks in an organization. The term refers to the type of risks the organization is willing to pursue, as well as amount of risk and the level of risk.
Risk appetite is the amount of risk a company or other entity is willing to accept in pursuit of its mission.
This is the responsibility of the board to decide risk appetite of an enterprise. When considering the risk appetite levels for the enterprise, the following two major factors should be taken into account:
The enterprise's objective capacity to absorb loss, e.g., financial loss, reputation damage, etc.

The culture towards risk taking-cautious or aggressive. In other words, the amount of loss the

enterprise wants to accept in pursue of its objective fulfillment.
Incorrect Answers:
A, B: Aversion and hedging are related to each other and represents the avoidance of risk within the organization.
D: The acceptable variation relative to the achievement of an objective is termed as risk tolerance. In other words, risk tolerance is the acceptable deviation from the level set by the risk appetite and business objectives.
Risk tolerance is defined at the enterprise level by the board and clearly communicated to all stakeholders.
A process should be in place to review and approve any exceptions to such standards.
insert code

Question 42

You are the project manager of the NHQ project in Bluewell Inc. The project has an asset valued at $200,000 and is subjected to an exposure factor of 45 percent. If the annual rate of occurrence of loss in this project is once a month, then what will be the Annual Loss Expectancy (ALE) of the project?

Correct Answer: C
Section: Volume D
Explanation:
The ALE of this project will be $ 108,000.
Single Loss Expectancy is a term related to Quantitative Risk Assessment. It can be defined as the monetary value expected from the occurrence of a risk on an asset. It is mathematically expressed as follows:
SLE = Asset value * Exposure factor
Therefore,
SLE = 200,000 * 0.45
= $ 90,000
As the loss is occurring once every month, therefore ARO is 12. Now ALE can be calculated as follows:
ALE = SLE * ARO
= 90,000 * 12
= $ 108,000
insert code

Question 43

You are the project manager of HFD project. You have identified several project risks. You have adopted alternatives to deal with these risks which do not attempt to reduce the probability of a risk event or its impacts. Which of the following response have you implemented?

Correct Answer: D
Explanation/Reference:
Explanation:
Contingent response strategy, also known as contingency planning, involves adopting alternatives to deal with the risks in case of their occurrence. Unlike the mitigation planning in which mitigation looks to reduce the probability of the risk and its impact, contingency planning doesn't necessarily attempt to reduce the probability of a risk event or its impacts. Contingency comes into action when the risk event actually occurs.
Incorrect Answers:
A: Risk acceptance means that no action is taken relative to a particular risk; loss is accepted if it occurs. If an enterprise adopts a risk acceptance, it should carefully consider who can accept the risk. Risk should be accepted only by senior management in relationship with senior management and the board. There are two alternatives to the acceptance strategy, passive and active.
Passive acceptance means that enterprise has made no plan to avoid or mitigate the risk but willing to

accept the consequences of the risk.
Active acceptance is the second strategy and might include developing contingency plans and reserves

to deal with risks.
B: Risk mitigation attempts to reduce the probability of a risk event and its impacts to an acceptable level.
Risk mitigation can utilize various forms of control carefully integrated together. The main control types are:
Managerial(e.g.,policies)

Technical (e.g., tools such as firewalls and intrusion detection systems)

Operational (e.g., procedures, separation of duties)

Preparedness activities

C: Risk avoidance means to evade risk altogether, eliminate the cause of the risk event, or change the project plan to protect the project objectives from the risk event.
insert code

Question 44

Which of the following IS processes provide indirect information?
Each correct answer represents a complete solution. Choose three.

Correct Answer: A,B,C
is incorrect. Recovery testing is the direct evidence that the redundancy or backup controls work effectively. It doesn't provide any indirect information.
insert code

Question 45

Which of the following methods involves the use of predictive or diagnostic analytical tool for exposing risk factors?

Correct Answer: D
Section: Volume D
Explanation:
Cause-and-effect analysis involves the use of predictive or diagnostic analytical tool for exploring the root causes or factors that contribute to positive or negative effects or outcomes. These tools also help in identifying potential risk.
Incorrect Answers:
A: This analysis is not a method for exposing risk factors. It is used for analyzing scenarios.
B: Sensitivity analysis is the quantitative risk analysis technique that:
* Assist in determination of risk factors that have the most potential impact
* Examines the extent to which the uncertainty of each element affects the object under consideration when all other uncertain elements are held at their baseline values C: Fault tree analysis (FIA) is a technique that provides a systematic description of the combination of possible occurrences in a system, which can result in an undesirable outcome. It combines hardware failures and human failures.
insert code
  • ««
  • «
  • …
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2022-10-16.q179 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.