FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2022-10-16.q179 Dumps
  • ««
  • «
  • …
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • …
  • »
  • »»
Download Now

Question 46

You are the Risk Official in Bluewell Inc. You have detected much vulnerability during risk assessment process.
What you should do next?

Correct Answer: D
Section: Volume C
Explanation:
Vulnerabilities detected during assessment should be first evaluated for threat, impact and cost of mitigation. It should be evaluated and prioritized on the basis whether they impose credible threat or not.
Incorrect Answers:
A, C: These are the further steps that are taken after evaluating vulnerabilities. So, these are not immediate action after detecting vulnerabilities.
B: If detected vulnerabilities impose no/negligible threat on an enterprise then it is not cost effective to address it as risk.
insert code

Question 47

You are the project manager for GHT project. You need to perform the Qualitative risk analysis process. When you have completed this process, you will produce all of the following as part of the risk register update output except which one?

Correct Answer: A
Section: Volume D
Explanation:
Probability of achieving time and cost estimates is an update that is produced from the Quantitative risk analysis process. In Qualitative risk analysis probability of occurrence of a specific risk is identified but not of achieving time and cost estimates.
insert code

Question 48

Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?

Correct Answer: B
Explanation/Reference:
Explanation:
Sammy She certainly can create an assessment for a risk event for time cost, and scope. It is probable that a risk event may have an effect on just one or more objectives so an assessment of the objective is acceptable.
Incorrect Answers:
A: Just because Sammy is the project manager, it is not necessary that she is right.
C: Harry is incorrect as there are multiple approaches to risk assessment for a project D: Harry's reasoning is flawed as each objective can be reviewed for the risk's impact rather than the total project.
insert code

Question 49

Which of the following approaches to bring you own device (BYOD) service delivery provides the BEST protection from data loss?

Correct Answer: B
Section: Volume D
Explanation
insert code

Question 50

Which of the following is performed after a risk assessment is completed?

Correct Answer: A
insert code
  • ««
  • «
  • …
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2022-10-16.q179 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.