FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2024-06-22.q384 Dumps
  • ««
  • «
  • …
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • …
  • »
  • »»
Download Now

Question 91

You are the project manager for the NHH project. You are working with your project team to examine the project from four different defined perspectives to increase the breadth of identified risks by including internally generated risks. What risk identification approach are you using in this example?

Correct Answer: C
Section: Volume D
Explanation/Reference:
Explanation:
This is an example of SWOT analysis. SWOT analysis examines the strengths, weaknesses, opportunities, and threats within the project and generated from within the organization.
SWOT stands for Strengths, Weaknesses, Opportunities, and Threats. It is a part of business policy that helps an individual or a company to make decisions. It includes the strategies to build the strength of a company and use the opportunities to make the company successful. It also includes the strategies to overcome the weaknesses of and threats to the company.
Incorrect Answers:
A: Root cause analysis examines causal factors for events within the project.
B: Influence diagramming techniques examines the relationships between things and events within the project.
D: Assumptions analysis does not use four pre-defined perspectives for review.
insert code

Question 92

You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques to complete this process. Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis process?

Correct Answer: D
Section: Volume C
Explanation:
Organizational process asset is not a tool and technique, but an input to the quantitative risk analysis process.
Quantitative Risk Analysis is a process to assess the probability of achieving particular project objectives, to quantify the effect of risks on the whole project objective, and to prioritize the risks based on the impact to overall project risk. Quantitative Risk Analysis process analyzes the affect of a risk event deriving a numerical value. It also presents a quantitative approach to build decisions in the presence of uncertainty. The inputs for Quantitative Risk Analysis are:
* Organizational process assets
* Project Scope Statement
* Risk Management Plan
* Risk Register
* Project Management Plan
Incorrect Answers:
A: Data gathering and representation technique is a tool and technique for the quantitative risk analysis process.
B: Expert judgment is a tool and technique for the quantitative risk analysis process.
C: Quantitative risk analysis and modeling techniques is a tool and technique for the quantitative risk analysis process.
insert code

Question 93

Shawn is the project manager of the HWT project. In this project Shawn's team reports that they have found a way to complete the project work cheaply than what was originally estimated earlier. The project team presents a new software that will help to automate the project work. While the software and the associated training costs
$25,000 it will save the project nearly $65,000 in total costs. Shawn agrees to the software and changes the project management plan accordingly. What type of risk response had been used by him?

Correct Answer: C
Section: Volume C
Explanation:
A risk event is being exploited so as to identify the opportunities for positive impacts. Exploit response is one of the strategies to negate risks or threats that appear in a project. This strategy may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized. Exploiting a risk event provides opportunities for positive impact on a project. Assigning more talented resources to the project to reduce the time to completion is an example of exploit response.
Incorrect Answers:
A: To avoid a risk means to evade it altogether, eliminate the cause of the risk event, or change the project plan to protect the project objectives from the risk event.
B: Accepting is a risk response that is appropriate for positive or negative risk events. It does not pursue the risk, but documents the event and allows the risk to happen. Often acceptance is used for low probability and low impact risk events.
D: Enhancing is a positive risk response that aims to increase the probability and/or impact of the risk event.
insert code

Question 94

You work as a project manager for BlueWell Inc. Your project is using a new material to construct a large warehouse in your city. This new material is cheaper than traditional building materials, but it takes some time to learn how to use the material properly. You have communicated to the project stakeholders that you will be able to save costs by using the new material, but you will need a few extra weeks to complete training to use the materials. This risk response of learning how to use the new materials can also be known as what term?

Correct Answer: C
Explanation/Reference:
Explanation:
When the project team needs training to be able to complete the project work it is a cost of conformance to quality.
The cost of conformance to quality defines the cost of training, proper resources, and the costs the project must spend in order to ascertain the expected levels of quality the customer expects from the project. It is the capital used up throughout the project to avoid failures. It consists of two types of costs:
Prevention costs: It is measured to build a quality product. It includes costs in training, document

processing, equipment, and time to do it right.
Appraisal costs: It is measured to assess the quality. It includes testing, destructive testing loss, and

inspections.
Incorrect Answers:
A: Benchmarking compares any two items, such as materials, vendors, or resources.
B: Cost-benefit analysis is the study of the benefits in relation to the costs to receive the benefits of a decision, a project, or other investment.
D: Team development describes activities the project manager uses to create a more cohesive and responsive project team.
insert code

Question 95

You are working as the project manager of the ABS project. The project is for establishing a computer network in a school premises. During the project execution, the school management asks to make the campus Wi-Fi enabled. You know that this may impact the project adversely. You have discussed the change request with other stakeholders. What will be your NEXT step?

Correct Answer: C
Explanation/Reference:
Explanation:
The first step after receiving any change request in a project must be first analyzed for its impact. Changes may be requested by any stakeholder involved with the project. Although, they may be initiated verbally, they should always be recorded in written form and entered into the change management and/or configuration management.
Incorrect Answers:
A, B, D: All these are the required steps depending on the change request. Any change request must be followed by the impact analysis of the change.
insert code
  • ««
  • «
  • …
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2024-06-22.q384 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.