FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISC Certification
  3. CSSLP Exam
  4. ISC.CSSLP.v2026-04-01.q148 Dumps
  • ««
  • «
  • …
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • …
  • »
  • »»
Download Now

Question 31

Fill in the blank with an appropriate phrase. A is defined as any activity that has an effect on defining, designing, building, or executing a task, requirement, or procedure.

Correct Answer: A
A technical effort is described as any activity, which has an effect on defining, designing, building, or implementing a task, requirement, or procedure. The technical effort is an element of technical management that is required to progress efficiently and effectively from a business need to the deployment and operation of the system.
insert code

Question 32

Which of the following elements of the BCP process emphasizes on creating the scope and the additional elements required to define the parameters of the plan?

Correct Answer: D
The scope and plan initiation process in BCP symbolizes the beginning of the BCP process. It emphasizes on creating the scope and the additional elements required to define the parameters of the plan. The scope and plan initiation phase embodies a check of the company's operations and support services. The scope activities include creating a detailed account of the work required, listing the resources to be used, and defining the management practices to be employed. Answer C is incorrect. The business impact assessment is a method used to facilitate business units to understand the impact of a disruptive event. This phase includes the execution of a vulnerability assessment. This process makes out the mission-critical areas and business processes that are important for the survival of business. It is similar to the risk assessment process. The function of a business impact assessment process is to create a document, which is used to help and understand what impact a disruptive event would have on the business. Answer A is incorrect. The business continuity plan development refers to the utilization of the information collected in the Business Impact Analysis (BIA) for the creation of the recovery strategy plan to support the critical business functions. The information gathered from the BIA is mapped out to make a strategy for creating a continuity plan. The business continuity plan development process includes the areas of plan implementation, plan testing, and ongoing plan maintenance. This phase also consists of defining and documenting the continuity strategy. Answer B is incorrect. The plan approval and implementation process involves creating enterprise-wide awareness of the plan, getting the final senior management signoff, and implementing a maintenance procedure for updating the plan as required.
insert code

Question 33

Frank is the project manager of the NHH Project. He is working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team. What document is Frank and the NHH Project team creating in this scenario?

Correct Answer: A
The risk management plan, part of the comprehensive management plan, defines how risks will be identified, analyzed, monitored and controlled, and even responded to. A Risk management plan is a document arranged by a project manager to estimate the effectiveness, predict risks, and build response plans to mitigate them. It also consists of the risk assessment matrix. Risks are built in with any project, and project managers evaluate risks repeatedly and build plans to address them. The risk management plan consists of analysis of possible risks with both high and low impacts, and the mitigation strategies to facilitate the project and avoid being derailed through which the common problems arise. Risk management plans should be timely reviewed by the project team in order to avoid having the analysis become stale and not reflective of actual potential project risks. Most critically, risk management plans include a risk strategy for project execution. Answer C is incorrect. The project management plan is a comprehensive plan that communicates the intent of the project for all project management knowledge areas. Answer B is incorrect. The project plan is not an official PMBOK project management plan. Answer D is incorrect. The resource management plan defines the management of project resources, such as project team members, facilities, equipment, and contractors.
insert code

Question 34

Which of the following rated systems of the Orange book has mandatory protection of the TCB?

Correct Answer: B
Explanation/Reference:
Explanation: A B-rated system of the orange book has mandatory protection of the trusted computing base (TCB).
Trusted computing base (TCB) refers to hardware, software, controls, and processes that cause a computer system or network to be devoid of malicious software or hardware. Maintaining the trusted computing base (TCB) is essential for security policy to be implemented successfully.
insert code

Question 35

DRAG DROP
Drag and drop the appropriate principle documents in front of their respective functions.

Correct Answer:


The various principle documents of transformation are as follows: CNSSP 22: It establishes a national risk management policy for national security systems. CNSSI 1199: It creates the technique in which the national security community classifies the information and information systems with regard to confidentiality, integrity, and availability. CNSSI 1253: It combines DCID 6/3, DOD Instructions 8500.2, NIST SP 800-53, and other security sources into a single cohesive repository of security controls. CNSSI 1253 A.
It offers the techniques to assess adequacy of each security control. CNSSI 1260: It provides guidance to organizations with the characterization of their information and information systems. NIST 800-37, Revision 1: It defines the certification and accreditation (C & A) process. The NIST 800-37, Revision 1 is a combination of DNI, DoD, and NIST.
insert code
  • ««
  • «
  • …
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISC.CSSLP.v2026-04-01.q148 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.