FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISQI Certification
  3. CTAL-TM-001 Exam
  4. ISQI.CTAL-TM-001.v2025-07-24.q115 Dumps
  • ««
  • «
  • …
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • …
  • »
  • »»
Download Now

Question 66

Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk? 3 credits

Correct Answer: D
insert code

Question 67

Your application development team is performing "test-driven" development. This is a core principal of which software development model? [1]

Correct Answer: C
Test-driven development (TDD) is a core principle of Agile software development. In TDD, test cases are created before the code is written, and the code is developed to pass these tests. This approach emphasizes requirements and solutions evolving through collaborative effort and is a key practice in Agile methodologies12.
Reference:
The Agile Alliance describes TDD as a style of programming tightly interwoven with coding, testing, and design, which is a fundamental aspect of Agile development3. Wikipedia also notes that TDD is related to the test-first programming concepts of extreme programming, an Agile methodology This is because test-driven development (TDD) is a style of programming in which coding, testing, and design are tightly interwoven. TDD is a core principle of agile software development, which is an iterative and adaptive approach that values customer collaboration, working software, and responding to change. Agile Alliance Reference: Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association, ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration, What is Test Driven Development (TDD)? | Agile Alliance
insert code

Question 68

Which of the following is a factor that is likely to increase the test estimate? [1]

Correct Answer: A
A test estimate is an approximation of the amount of effort, time, and resources required to perform testing activities for a software project1. A test estimate can be influenced by various factors, such as the size, complexity, and quality of the software, the scope, objectives, and approach of the testing, the skills, experience, and availability of the test team, the tools, methods, and standards used for testing, and the constraints, risks, and assumptions related to the project2. One of the factors that is likely to increase the test estimate is the use of a new technology. A new technology is a technology that is unfamiliar or unproven to the test team or the organization, such as a new programming language, framework, platform, or tool3. The use of a new technology can increase the test estimate because it may require more time and effort to learn, understand, and apply the technology, as well as to deal with potential issues, challenges, or limitations that may arise from the technology. Therefore, option A is the correct answer. Option B is incorrect because a requirement for high level test documentation is not a factor that is likely to increase the test estimate, but rather a factor that is likely to increase the test documentation effort. Test documentation is the set of documents that describe the test basis, test objectives, test design, test procedures, test results, and test evaluation of a software project. A requirement for high level test documentation means that the test documents need to be detailed, comprehensive, and consistent, which may require more time and effort to produce, review, and maintain. However, this does not necessarily affect the test estimate, as the test documentation effort can be considered as a separate or parallel activity to the test execution effort. Option C is incorrect because assigned personnel who are experienced on working with similar projects in similar environments is not a factor that is likely to increase the test estimate, but rather a factor that is likely to decrease the test estimate. Experienced personnel are personnel who have the relevant knowledge, skills, and abilities to perform the testing activities for a software project. Assigned personnel who are experienced on working with similar projects in similar environments can decrease the test estimate because they may require less time and effort to understand, design, implement, and execute the tests, as well as to deal with potential issues, challenges, or limitations that may arise from the project. Option D is incorrect because static test data is not a factor that is likely to increase the test estimate, but rather a factor that is likely to decrease the test estimate. Test data is the data that is used as input or output for the tests. Static test data is test data that is fixed and predefined, and does not change during the test execution. Static test data can decrease the test estimate because it may require less time and effort to create, manage, and maintain, as well as to ensure the validity, reliability, and traceability of the test data. Reference: 1: ISTQB Glossary, Test Estimate 2: ISTQB Advanced Level Test Manager Syllabus, Section 3.1.1 3: What is New Technology? - Definition from Techopedia : The Impact of New Technologies on Software Testing : ISTQB Glossary, Test Documentation : ISTQB Glossary, Experienced-Based Test Technique : ISTQB Glossary, Test Data : ISTQB Glossary, Static Test Data : Test Manager - ISTQB not-for-profit association : [ISTQB Foundation Level #38 - Test Estimation Techniques - Software Testing Mentor] : [What are the estimation techniques in software testing?]
insert code

Question 69

Which of the following are valid reasons for adopting a different life cycle (from the V model), for increments after the first year? 2 credits i. We do not have a clear understanding of the requirements from a customer perspective.
ii. We see the risk of delivering requested functionality late as being higher than the risk of delivering a lower quality product.
iii. We do not have a budget for additional regression testing which is needed to ensure that existing functionality is not compromised by future iterations.
iv. The company test strategy does not fit well within the V life cycle model.

Correct Answer: A
Explanation/Reference:
Explanation:
Topic 6, Scenario 6, V4 "Independent Test Team"
You have for a while been trying to hire a second test automation specialist for your test team However, you did not have any luck in finding a suitable candidate. So now, you have been asked by IT management of XYZ to forward a proposal with alternative solutions for building an automated regression test suite at system test level over a period of 2 years including needed training and eventual handover to the test team.
insert code

Question 70

Which of the following can demotivate a tester? [1]

Correct Answer: D
This can demotivate a tester because it implies that the tester's work is not valued or respected by the management or the stakeholders. It also suggests that the tester's efforts and skills are wasted or ineffective, as the product quality is compromised and the customer satisfaction is reduced. Testing is cut short when there is insufficient time, budget, or resources allocated for testing, or when there is pressure to release the product without adequate testing. This can lead to frustration, dissatisfaction, and loss of confidence among the testers. Top 6 things that demotivate a developerHow to Demotivate Your Best Employees References:
* Top 6 things that demotivate a developer - Amsterdam Standard
* How to Demotivate Your Best Employees - HBS Working Knowledge
insert code
  • ««
  • «
  • …
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISQI.CTAL-TM-001.v2025-07-24.q115 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.