FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISQI Certification
  3. CTAL-TM-001 Exam
  4. ISQI.CTAL-TM-001.v2025-07-24.q115 Dumps
  • ««
  • «
  • …
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
Download Now

Question 111

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a.Any deviation from the procedures described in the test strategy document
b.The overall estimated costs, timescales and resource requirements
c.A detailed schedule of testing activities
d.The development deliverables to be tested
e.Which test staff members (names) will be involved and when
f.Level of requirements coverage achieved
Which THREE of the above mentioned characteristics relate to the master test plan? 1 credit

Correct Answer: B,D,E
insert code

Question 112

Which of the following statements is true regarding Fault Tree Analysis? [1]

Correct Answer: A
Fault Tree Analysis (FTA) is a technique used to analyze the causes of faults (defects). The technique visually models how logical relationships between failures, human errors, and external events can combine to cause specific faults to disclose1. FTA can help to determine the root cause of observed and potential failures by tracing back the fault events to their initiating causes and identifying the combinations of events that can lead to the fault occurrence2. Therefore, option A is the correct answer. Option B is incorrect because FTA is not used to select the pairs of items to be used in pairwise testing, which is a technique to generate test cases based on the combinations of two input parameters. Option C is incorrect because FTA is not a formal technique used to identify the likely effects of risks, which are uncertain events or conditions that may have a positive or negative impact on the project objectives. Option D is incorrect because FTA is not used to target defect-based testing, which is a testing technique that uses information about the types, causes, and locations of defects discovered in previous projects to guide the selection, creation, and prioritization of test cases. References: 1: Fault Tree Analysis | ISTQB Glossary 2: Fault Tree Analysis (FTA) - Software Testing Genius : ISTQB Glossary, Pairwise Testing : ISTQB Glossary, Risk : ISTQB Glossary, Defect-Based Test Technique : Fault Tree Analysis (FTA) - Software Testing Genius : Fault Tree Analysis | ISTQB Glossary
insert code

Question 113

Which one of the following is NOT a determining factor when considering the optimal time to conduct a document review? SELECT ONE OPTION

Correct Answer: B
insert code

Question 114

Relying only on the information provided in the scenario, select the TWO items and/or features for which sufficient information is available to proceed with test design. 2 credits

Correct Answer: A,C
Explanation/Reference:
Explanation:
insert code

Question 115

You are managing the testing for a bank card project. The testing was scheduled to take 10 weeks but by the time the software was developed only six weeks were available for testing Knowing there were a lot of risks with the software your team started testing activities early by overseeing code reviews, defining acceptance criteria by working with the users and by doing all lest creation prior to the code arriving You are now three days away from the go-live date Your testing has mitigated all the high and medium risk items leaving only the low-risk elements unmitigated by testing You estimate it will take two weeks to manually test the low-risk elements At this point what should you do?

Correct Answer: D
Context Analysis:
With limited time, testing all low-risk elements is not feasible. Depth testing on a representative low-risk element helps assess potential residual risk efficiently.
Evaluation of Options:
A . Automate the testing of the untested elements to ensure they are covered:
Incorrect. There isn't enough time to implement automation.
B . Block the go-live and start testing the low-risk elements immediately:
Incorrect. Blocking the release may not be acceptable if high and medium risks are already mitigated.
C . Transfer the risk of the untested low-risk items to the help desk:
Incorrect. While a potential fallback, it doesn't address residual risk proactively.
D . Select one of the low-risk elements and perform depth testing to assess the residual risk:
Correct. This provides quick insights into potential risks and helps make an informed go/no-go decision.
Syllabus Alignment:
ISTQB emphasizes prioritizing risk mitigation through targeted testing (TM-1.3.4).
Reference:
ISTQB Advanced Level Test Management Syllabus (TM-1.3.4)
insert code
  • ««
  • «
  • …
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
[×]

Download PDF File

Enter your email address to download ISQI.CTAL-TM-001.v2025-07-24.q115 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.