Defect Management
Assume you are working on a defect management process to be used by a software organization to track the current status of the defects reports for several projects.
When a defect is found for investigation a defect report is created in "Opened" state that is the unique initial state. The defect report status has also a unique finale state that is the "Closed" state.
The following state transition diagram describes the states of this defect management process:
where only the initial ("Opened") and final ("Closed") states are indicated while the remaining states (V, W, X, Y, Z) have yet to be named.
Which of the following assignments would you expect to best complete the defect management process?
Number of correct responses: 1
K32 credits
The main objectives the senior management team wants to achieve are:
-
to reduce the costs associated with dynamic testing
-
to use reviews to ensure that the project is on course for success and following the plan
-
to use reviews as a well-documented and effective bug-removal activity following a formal process with well-defined roles
-
to determine the effectiveness of reviews in terms of phase containment
-
to improve phase containment effectiveness
Which of the following answers would you expect to describe the best way to achieve these objectives?
K4 3 credits
Your company is installing a third-party enterprise-wide business software package. This is the first time the company has done anything like this.
Which technique would be the best one to use to estimate the testing effort? [3]
Test Management
In the test strategy document your organization declares:
- to adopt a V-model development lifecycle, with three formal levels of testing: unit, integration and system testing
- to use a blended risk-based and regression-averse testing strategy for each level of testing The following is an excerpt of the "approach" section for the system test plan document of a new project:
"Testing will only use manual tests. Due to the short period of time for test execution, the following activities will be performed in parallel with test execution: Test planning, test analysis and test design.
Basic metrics will be taken for test effort (i.e. person-hours), test cases executed (passed/failed), and incidents (no more metrics, such as code coverage, will be collected)." In the system test plan, no deviations from the test strategy are described.
Based only on the given information, which of the following statements is true?