FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISQI Certification
  3. CTAL-TM_Syll2012 Exam
  4. ISQI.CTAL-TM_Syll2012.v2024-08-20.q103 Dumps
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • »
Download Now

Question 81

Test Management
You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.
At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.
Which of the following statements is true in this context?

Correct Answer: B
insert code

Question 82

Test Tools and Automation
In your organization the following tools of the same vendor are currently in use: a requirements management tool, a test management tool and a bug tracking tool.
You are the Test Manager.
You are currently evaluating a test automation tool of the same vendor (to complete the vendor's tool suite) against an interesting open-source test automation tool under the GNU GPL (General Public License).
There are no initial costs associated to that open-source tool.
Which of the following statements associated to the selection of the open-source tool is correct in this scenario?
Number of correct responses: 1
K2 1 credit

Correct Answer: B
insert code

Question 83

People Skills - Team Composition
Assume you are managing the system testing execution phase of a project.
The system test execution period for that project is scheduled for eighteen weeks and the release date is scheduled at the end of system testing.
During the sixth week of system test execution, at the staff meeting, the project manager informs you that the project deadlines are changed and the release date that is only three weeks ahead.
This new release will not allow the completion of the system tests. Suppose also that you have followed a risk-driven test approach for this project.
Which of the following statements represents the worst way to lead your test team in the next three weeks?

Correct Answer: A
Explanation/Reference:
insert code

Question 84

You just handed over the Defect Accepted and Deferred report to your Maintenance team.
Which testing activity are you performing? [1]

Correct Answer: D
The correct answer is D. Test Closure. This is because test closure is the final activity of the test process, in which the test team evaluates the test results, reports the outcomes, identifies the lessons learned, and hands over the testware and the defect reports to the maintenance team. The Defect Accepted and Deferred report is a document that lists the defects that have been accepted by the stakeholders and deferred to be fixed in future releases. By handing over this report to the maintenance team, the test team is performing the test closure activity. Test Closure - ISTQB not-for-profit association References: Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association, ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration, Test Closure - ISTQB not-for-profit association
insert code

Question 85

The Test Manager must assemble team members that have which of the following characteristics? [1]

Correct Answer: C
A test manager must assemble team members that will spark informal cross training among themselves. This means that the team members are willing and able to share their knowledge, skills, and experiences with each other, and learn from each other's feedback and suggestions. This can improve the team's performance, productivity, and quality, as well as foster a collaborative and supportive culture. Cross training can also help the team members to develop new competencies, fill skill gaps, and handle different roles and tasks when needed. Top 10 Leadership Qualities to Distinguish a Test ManagerTest manager roles and responsibilities (with FAQs) References:
Top 10 Leadership Qualities to Distinguish a Test Manager - Software Test Professionals Test manager roles and responsibilities (with FAQs) - Indeed
insert code
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • »
[×]

Download PDF File

Enter your email address to download ISQI.CTAL-TM_Syll2012.v2024-08-20.q103 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.