FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISQI Certification
  3. CTAL_TM_001 Exam
  4. ISQI.CTAL_TM_001.v2026-03-16.q141 Dumps
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • …
  • »
  • »»
Download Now

Question 81

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a.Any deviation from the procedures described in the test
b.strategy document
c.The overall estimated costs, timescales and resource
d.requirements
e.A detailed schedule of testing activities
f.The development deliverables to be tested
g.Which test staff members (names) will be involved and when
h.Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit

Correct Answer: C,E
Topic 10, Scenario 10, V3 "Online Application"
The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid Application Development (RAO) approach.
insert code

Question 82

Which testing metric identifies defect density? [1]

Correct Answer: B
Defect density is a testing metric that measures the number of defects identified in a component or system divided by the size of the component or system (expressed in standard measurement terms, e.g., lines-of-code, number of classes or function points)1. Defect density is a product metric, as it evaluates the quality or reliability of a software product2. Therefore, option B is the correct answer. Option A is incorrect because project metrics are metrics that measure the characteristics of the software project, such as cost, schedule, effort, scope, or resources3. Option C is incorrect because process metrics are metrics that measure the characteristics of the software process, such as effectiveness, efficiency, productivity, or maturity. Option D is incorrect because people metrics are metrics that measure the characteristics of the software personnel, such as skills, experience, motivation, or satisfaction. Reference: 1: Defect Density | ISTQB Glossary 2: Software Testing Metrics: What is, Types & Example 3: [Project Metrics - Software Testing Fundamentals] : [Process Metrics - Software Testing Fundamentals] : [People Metrics - Software Testing Fundamentals]
insert code

Question 83

You are managing the testing for a bank card project. The testing was scheduled to take 10 weeks but by the time the software was developed only six weeks were available for testing Knowing there were a lot of risks with the software your team started testing activities early by overseeing code reviews, defining acceptance criteria by working with the users and by doing all lest creation prior to the code arriving You are now three days away from the go-live date Your testing has mitigated all the high and medium risk items leaving only the low-risk elements unmitigated by testing You estimate it will take two weeks to manually test the low-risk elements At this point what should you do?

Correct Answer: D
* Context Analysis:
* With limited time, testing all low-risk elements is not feasible. Depth testing on a representative low-risk element helps assess potential residual risk efficiently.
* Evaluation of Options:
* A. Automate the testing of the untested elements to ensure they are covered:
* Incorrect. There isn't enough time to implement automation.
* B. Block the go-live and start testing the low-risk elements immediately:
* Incorrect. Blocking the release may not be acceptable if high and medium risks are already mitigated.
* C. Transfer the risk of the untested low-risk items to the help desk:
* Incorrect. While a potential fallback, it doesn't address residual risk proactively.
* D. Select one of the low-risk elements and perform depth testing to assess the residual risk:
* Correct. This provides quick insights into potential risks and helps make an informed go/no- go decision.
* Syllabus Alignment:
* ISTQB emphasizes prioritizing risk mitigation through targeted testing (TM-1.3.4).
References:
ISTQB Advanced Level Test Management Syllabus (TM-1.3.4)
insert code

Question 84

You have been seeing a high number of rejections of defect reports The developers are complaining that they do not understand what the problem is. even though they have been supplied with screenshots. You have checked a number of the 'problem' defect reports and have not found any information that is missing. The descriptions are very detailed and include all the necessary information in a long descriptive paragraph.
What change should you recommend that should help with the developer s problems?

Correct Answer: D
* Context Analysis:
* Long descriptive paragraphs are difficult to parse, even if they contain all necessary information.
Developers need concise, structured information for quick understanding.
* Evaluation of Options:
* A. Instruct your team to make all defects high priority:
* Incorrect. Changing priority does not address the clarity issue in defect reports.
* B. Highlight all the information and walk through it with the developers:
* Incorrect. This is time-consuming and not scalable as a general solution.
* C. Email screenshots to developers in addition to attaching them to defect reports:
* Incorrect. Duplication of information does not solve the clarity problem.
* D. Separate out the steps to reproduce the defect in the description so it is clearer for the developers and easier to find:
* Correct. Structuring defect reports improves clarity and makes them easier to process.
* Syllabus Alignment:
* ISTQB recommends clear and concise defect reports to facilitate understanding and resolution (TM-2.3.5).
References:
ISTQB Advanced Level Test Management Syllabus (TM-2.3.5)
insert code

Question 85

Explain how the above mentioned report may differ from a report that you produce for the project manager, who is a test specialist Select TWO items from the following options that can be used to report to the project manager and would not be included in a report to senior management. 1 credit

Correct Answer: B,D
insert code
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISQI.CTAL_TM_001.v2026-03-16.q141 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.