Your company is currently using a fixed duration for a job type while scheduling work orders. This causes cascading delays, resulting in lower utilization of the resources.
To address this issue, you propose the use of predictive work duration (powered by AI) to help provide more realistic durations.
You need to advise the management team on the factors dispatchers can use to predict the duration of any given booking or requirement.
Which three factors can be used? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You are a Dynamics 365 for Field Service Mobile customizer.
Your mobile technicians indicate that when in offline mode, they do not have access to the same data set that is available online. Offline mode contains less account and work order data, and users cannot see warehouses.
You need to determine which updates to make within the mobile project so that technicians can see the appropriate information.
Which three actions should you choose? Each correct answer presents a complete solution.
You are a Dynamics 365 for Field Service Administrator. You are working with your company's scheduling team on requirements for a new schedule board view.
The team needs a schedule board view where they only see work orders with a priority of Critical.
Which three steps should you perform, in sequence, to meet their need? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

You are a Dynamics 365 for Field Service consultant.
One of your Dynamics 365 customers wants to decrease the number of repair appointments by sending fewer technicians onsite.
You need to provide a recommendation of which solution your customer should use to achieve their request.
What should you recommend?
Drag and Drop Question
You are implementing Microsoft Dynamics 365 Field Service for an organization.
The organization has a dispatcher who schedules resources across multiple time zones. The dispatcher requests for the resources categorized by time zone, so they could quickly schedule the appropriate resources and visualize multiple resources per time zone on the schedule.
You need to configure the schedule board to accommodate this request.
Which three actions should you recommend be performed in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
NOTE: Each correct selection is worth one point.