An Agile team expects a velocity of 8.During sprint planning, the stories were estimatedand prioritized in the following order:
Story A_4Story Points Story B_2Story Points Story C_3 Story Points Story D_2Story Points
Which stories should the team include in Sprint 1, without splitting the stories?