FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMP-CN Exam
  4. PMI.PMP-CN.v2024-04-19.q212 Dumps
  • ««
  • «
  • …
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • …
  • »
  • »»
Download Now

Question 116

公司總是為其專案從當地公司獲得非常專業的服務。在監管專案的規劃階段,專案經理被告知,由於意外的重大事件,當地供應商將無法運作。可以選擇從其他國家的公司僱用相同的服務。
遇到這種情況,專案經理該怎麼辦?

Correct Answer: B
Explanation
According to the PMBOK Guide, 6th edition, procurement management is the process of purchasing or acquiring the products, services, or results needed from outside the project team to perform the work.
Procurement management can be done in a virtual environment, where the project manager and the vendors communicate and collaborate using online tools and platforms. This can help the project manager to overcome thechallenges posed by the unexpected major event that prevents the local vendors from operating. Planning to execute the procurement tasks in a virtual environment can also help the project manager to maintain the project schedule, scope, and quality, as well as to manage the risks and stakeholder expectations. References:
PMBOK Guide, 6th edition, Chapter 12: Project Procurement Management1; PMI, 2023, PMP Exam Content Outline2, Domain II: Process, Task 8: Plan and manage procurement activities.
1: PMBOK Guide, 6th edition 2: [PMP Exam Content Outline]
insert code

Question 117

生產團隊很快將開始他們的第一個敏捷項目。團隊或管理層中沒有人具備敏捷知識。培訓經理只能資助三名註冊學生。
將左側的團隊角色與右側的正確培訓課程相匹配。(使用所有三個團隊角色。)

Correct Answer:
insert code

Question 118

一家公司計劃啟動一個涉及新技術的專案。該項目需要獲得批准。
專案經理該做什麼?

Correct Answer: D
Explanation
The project manager should analyze the cost and identify the project benefits before initiating a project involving a new technology. This is because the project manager needs to justify the business case and the return on investment (ROI) of the project to the project sponsor and other stakeholders who will approve the project. The projectmanager should also consider the alignment of the project with the organizational strategy and goals. The project manager should use tools and techniques such as cost-benefit analysis, net present value (NPV), internal rate of return (IRR), and benefit-cost ratio (BCR) to evaluate the feasibility and viability of the project.
Option A is not a good action, as reviewing the cost and schedule baselines for execution is a planning activity that should be done after the project is approved and initiated. The project manager should not assume the project baselines before conducting a thorough analysis of the project scope, requirements, resources, and constraints.
Option B is not a good action, as identifying the risks in implementing the new technology is also a planning activity that should be done after the project is approved and initiated. The project manager should not focus on the potential negative outcomes of the project before establishing the positive outcomes and benefits of the project.
Option C is not a good action, as defining change management for the new technology is also a planning activity that should be done after the project is approved and initiated. The project manager should not anticipate the changes that may occur during the project execution before defining the project scope, objectives, and deliverables. References:
[PMBOK Guide], 6th edition, page 33, section 1.2.3
[PMP Exam Content Outline], page 8, task 1 under domain 1
insert code

Question 119

一個石油和天然氣項目在尚未獲得項目全額資金的情況下啟動。剩餘資金將在項目執行期間獲得。剩餘資金的獲取被推遲了幾個月,導致所有承包商暫停工作。
項目經理應該採取什麼措施來防止這種情況發生?

Correct Answer: C
insert code

Question 120

專案團隊很難理解有關需求的技術細節。該資訊最初不是由客戶提供的,但該資訊在當前迭代中對於澄清需要如何完成任務至關重要。
專案經理應該如何應對這種情況?

Correct Answer: A
Explanation
In agile projects, the customer is an integral part of the project team and should be involved in the planning, execution, and review of each iteration. By educating the customer on the agile principles and practices, the project manager can ensure that the customer understands the value of frequent feedback, collaboration, and adaptation. By having the customer participate in daily standup meetings, the project manager can facilitate direct communication between the customer and the development team, and enable quick resolution of any issues or ambiguities regarding the requirements. This will help the project team to deliver the most valuable features to the customer in each sprint. References: PMBOK Guide, 7th edition, pages 55, 56, 57, 58, 59, 60,
61, 62, 63, 64, and 65. World of Project Management.
insert code
  • ««
  • «
  • …
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMP-CN.v2024-04-19.q212 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.