FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMP-CN Exam
  4. PMI.PMP-CN.v2024-04-19.q212 Dumps
  • ««
  • «
  • …
  • 34
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40
  • 41
  • 42
  • 43
  • …
  • »
  • »»
Download Now

Question 186

從事一個項目的兩個項目團隊成員之間經常會發生衝突。這對項目造成了負面影響。
項目經理應該如何處理這種情況呢?

Correct Answer: B
insert code

Question 187

項目經理被分配到一個關鍵的軟件開發項目。該團隊正在使用混合方法,並將開發分為四個衝刺。在衝刺三結束時,項目經理髮現掙值 (EV) 為 500,000 美元,計劃價值 (PV) 為 550,000 美元。
項目經理應該做什麼?

Correct Answer: C
insert code

Question 188

在專案結束階段,專案經理發現客戶沒有使用某項特定服務。然後,客戶非正式地要求專案經理將服務延長到合約結束日期之後。合約中明確規定了服務期限。
專案經理應該如何解決這種情況才能結束專案?

Correct Answer: A
Explanation
= The project manager should issue a change request and activate the formal change control process to address the situation, because extending the service beyond the contract end date is a deviation from the original scope and schedule of the project. The change request should include the rationale, impact, and benefits of the proposed change, as well as the alternatives and risks. The change request should then be submitted to the appropriate authority (such as the project sponsor, steering committee, or change control board) for review and approval. The formal change control process ensures that the change is properly evaluated, authorized, communicated, and documented. The project manager should not accept, deny, or escalate the request without following the change control process, as this may violate the terms of the contract, compromise the quality of the project deliverables, or create conflicts with the client or other stakeholders. The project manager should also update the project management plan, the project schedule, the project budget, and the project baselines to reflect the approved change, and monitor and control the project performance accordingly. The project manager should also include the change and its outcome in the lessons learned documentation for future reference and improvement. References: = Project Management Professional (PMP) Exam Content Outline, A Guide to the Project Management Body of Knowledge (PMBOK Guide), Sixth Edition, Termination of Service Contract: Everything You Need to Know - UpCounsel, The 7-step project closure checklist to end on a high note - Teamwork
insert code

Question 189

專案經理管理矩陣組織中的多個資訊技術 (IT) 專案。專案經理安排與一位職能經理舉行會議,協調兩個軟體開發專案的測試支援。不幸的是,職能經理無法參加會議,並通知專案經理可能沒有任何資源可用於測試軟體。
專案經理該做什麼?

Correct Answer: D
Explanation
According to the PMBOK Guide, testing is a quality control process that involves verifying that a product, service, or result meets the specified requirements and standards. Testing is an essential activity in software development projects, as it helps to ensure the functionality, reliability, usability, and security of the software.
Testing can be performed at different levels and stages of the software development life cycle, such as unit testing, integration testing, system testing, acceptance testing, etc. Testing can be done by different roles and stakeholders, such as developers, testers, customers, users, etc.
In this question, the project manager is managing multiple IT projects in a matrix organization, where the project team members are shared with other projects or functional units. The project manager schedules a meeting with one of the functional managers to coordinate testing support for two software development projects. However, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software. This can create a problem for the project manager and the project team, as it may affect the quality, scope, schedule, and cost of the projects. To resolve this issue, the project manager should take the following action:
Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained. The project manager should communicate with the project team members and discuss the testing requirements, expectations, and constraints for the two software development projects. The project manager should also involve the project team members in identifying and evaluating the possible alternatives and solutions to obtain the testing support, such as reallocating the existing resources, requesting additional resources, outsourcing the testing activities, modifying the testing plan, etc. The project manager should also facilitate the decision-making process and select the best option that meets the project objectives and stakeholder needs. This will help to ensure the quality and success of the software development projects, and to foster a collaborative and participative environment within the project team.
The other options are not correct because they do not provide a valid way to resolve the issue of testing support. Option A is wrong because it suggests that the project manager should meet with a procurement specialist to negotiate with a company that specializes in software testing, without consulting with the project team or the customer. This would be premature, costly, and risky, as it maynot align with the project scope, budget, schedule, or quality requirements. Option B is wrong because it implies that the project manager should request a meeting with the sponsor to change the scope to allow the development team to conduct testing, without exploring other alternatives or solutions. This would be impractical, ineffective, and inefficient, as it may not ensure the quality and reliability of the software, and may increase the workload and responsibility of the development team. Option C is wrong because it assumes that the project manager can discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software, without involving the project team or the functional manager. This would be inappropriate, incomplete, and inaccurate, as it may not reflect the actual testing needs and expectations of the projects, and may create conflict or confusion among the stakeholders. References:
PMBOK Guide, 6th edition, pages 286-287, 318-319, 374-375
Software Testing - Project Management Knowledge
Software Testing - Project Management Institute
Software Testing in Project Management
Project Management for Software Testing
insert code

Question 190

由於供應商出現問題,項目團隊遇到了進度延誤的情況。有些任務處於關鍵路徑上。
遇到這種情況,項目經理應該怎麼辦?

Correct Answer: A
insert code
  • ««
  • «
  • …
  • 34
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40
  • 41
  • 42
  • 43
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMP-CN.v2024-04-19.q212 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.