FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMP-CN Exam
  4. PMI.PMP-CN.v2024-04-19.q212 Dumps
  • ««
  • «
  • …
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40
  • 41
  • 42
  • 43
  • 44
  • »
Download Now

Question 206

專案經理正在為一家新創公司進行一個專案。本公司透過學習平台推出基於雲端的敏捷專案管理和DevOps培訓模組,支援多種自訂進度和虛擬學習形式。在最近的一次衝刺中,品質保證團隊未能在部署前徹底檢查模組,導致客戶體驗不佳。
專案經理面臨下列哪些問題?

Correct Answer: D
Explanation
project manager is facing an escaped defect issue for the project that launched cloud-based agile project management and DevOps training modules via the learning platform. An escaped defect is a defect that is not detected or corrected during the development or testing phase, and reaches the end-users or customers, causing dissatisfaction or harm. The project manager should take immediate action to fix the defect and prevent it from recurring, as well as to communicate with the stakeholders and apologize for the inconvenience. The project manager should also review the quality assurance process and improve the inspection and verification methods. The project manager is not facing a nonconformance issue, an unmet planned-to-done ratio, or an undetected error, as these terms do not describe the situation accurately or completely. References: PMBOK Guide, 6th edition, page 286, Free PMP Practice Exam Questions - 120 Sample Test Questions
insert code

Question 207

一名關鍵項目團隊成員在關鍵項目迭代期間請病假。項目發起人了解到,迭代結束版本的任何延遲都會令業務利益相關者感到不滿。儘管所有團隊成員都是跨職能的,但他們也都在接近滿負荷工作。
項目經理應該如何應對這種情況?

Correct Answer: B
insert code

Question 208

專案團隊很難理解有關需求的技術細節。該資訊最初不是由客戶提供的,但該資訊在當前迭代中對於澄清需要如何完成任務至關重要。
專案經理應該如何應對這種情況?

Correct Answer: D
insert code

Question 209

在使用者驗收測試期間發現的缺陷可能會嚴重影響系統的效能。
專案團隊表示,這項缺陷會使交付日期面臨風險。
應執行哪個風險管理流程?

Correct Answer: D
Explanation
According to the PMBOK Guide, the risk management process that should be performed in this situation is Plan Risk Responses1. This process involves developing options and actions to enhance opportunities and reduce threats to the project objectives1. In this case, the defect identified during user acceptance testing is a threat that could affect the system performance and the delivery date. Therefore, the project manager should plan risk responses to avoid, mitigate, transfer, or accept the risk, and to implement contingency plans if the risk occurs1. The other options are not appropriate for this situation, as they do not address the need to take action to deal with the risk.
Perform Qualitative Risk Analysis is the process of prioritizing risks based on their probability and impact1. It does not provide options and actions to handle the risks.
Monitor Risks is the process of tracking the implementation of risk responses, identifying and analyzing new risks, and evaluating risk process effectiveness1. It does not involve developing new risk responses.
Perform Quantitative Risk Analysis is the process of analyzing the effect of risks on the project objectives using numerical techniques1. It does not provide options and actions to handle the risks.
References: 1: PMBOK Guide, 7th edition, pages 97-99.
insert code

Question 210

一位專案經理最近被分配到一個處於執行階段且遇到障礙的專案。在審查流程和程序時,專案經理注意到與先前遇到類似障礙的專案的相似之處。專案經理審查任務進度表,發現某些任務遠遠落後於預期。在與專案團隊交談時,專案經理確認團隊完全遵循流程。
專案經理該做什麼?

Correct Answer: B
Explanation
According to the PMBOK Guide, 7th edition, one of the key principles for project delivery is to "tailor the delivery approach based on context" (p. 11). This principle implies that the project manager should adapt the processes and practices to suit the specific needs and characteristics of the project, rather than following a rigid or predefined methodology. The project manager should review and amend the processes to ensure only value-adding activities are present, as this will help to eliminate waste, optimize efficiency, and improve performance. Reviewing the resources, updating the variation register, or updating the schedule are not effective ways to handle the situation, as they do not address the root cause of the problem, which is the misalignment between the processes and the project context. References: PMBOK Guide, 7th edition, p.
11; PMP Exam Content Outline, Domain II: Process, Task 2.
insert code
  • ««
  • «
  • …
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40
  • 41
  • 42
  • 43
  • 44
  • »
[×]

Download PDF File

Enter your email address to download PMI.PMP-CN.v2024-04-19.q212 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.