A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.
What should the project manager do?
A project manager was informed by their supplier that there will be an upcoming raw material shortage due to a regulatory change. What should the project manager do?
A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would be required 3 months prior to the project's finish date. During project execution, it was determined that the contract was required immediately.
What should project manager do?
A project team member just informed the project manager that the license for the software that the team uses to perform calculations has just expired. As a result, the team cannot continue with their project tasks.
What should the project manager do first?
A project manager recently finished a project and started managing a new project with a different supervisor.
As part of the early project activities, the supervisor from the
original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor.
What should the project manager do to resolve this conflict?