FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMP Exam
  4. PMI.PMP.v2026-10-28.q120 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 1

While reviewing a project deliverable, there is a disagreement between the relevant stakeholders on whether or not to formally accept the deliverable. What tool should the project manager use to resolve the disagreement?

Correct Answer: A
insert code

Question 2

One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.
What should the project manager do next?

Correct Answer: A
insert code

Question 3

A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.
How should the project manager handle this issue?

Correct Answer: C
According to the PMBOKGuide Seventh Edition, one of the project management principles is to engage stakeholders actively and frequently. This means that the project manager should identify and analyze the needs, expectations, and interests of all stakeholders, and involve them appropriately throughout the project life cycle. The stakeholder register is a document that lists the key stakeholders, their roles, responsibilities, and level of influence on the project. The stakeholder engagement plan is a document that describes the strategies and actions to communicate with, manage, and influence the stakeholders.
In this scenario, the project manager has discovered that the local community was not included in the stakeholder register, which has caused them to oppose the project. This is a serious issue that can affect the project's performance, reputation, and acceptance. Therefore, the project manager should not disregard these stakeholders, as this would violate the principle of stakeholder engagement and potentially escalate the conflict. The project manager should also not just explain to the community members why they were not included as stakeholders, as this would not address their concerns or expectations. The best option is to update the stakeholder register and revise the stakeholder engagement plan, as this would allow the project manager to acknowledge the community as a stakeholder, assess their impact and interest, and develop appropriate strategies and actions to engage them effectively and proactively. References:
* PMBOKGuide Seventh Edition, page 9
* Project Management Principles 9-12, Episode 479: Project Management Principles 9-12 (Free)
insert code

Question 4

A project sponsor would like to include a new deliverable. The sponsor contacts the project manager in order to seek advice on the most efficient approach to complete the deliverable within the next 2 months.
What should the project manager do?

Correct Answer: C
When a new deliverable is proposed, the project manager should evaluate its impact on the project's scope, time, cost, and quality. A cost-benefit analysis is a systematic approach to estimate the strengths and weaknesses of alternatives and is used to determine options that provide the best approach to achieve benefits while preserving savings12. It involves comparing the expected costs of project actions to the expected benefits in order to choose the best option3.
References:
Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition.
ProjectManager.com. (2023). Cost-Benefit Analysis: A Quick Guide with Examples and Templates1.
Wrike.com. (2023). Cost-Benefit Analysis in Project Management Explained2.
Project-management.com. (2023). Cost Benefit Analysis - Formula, Example & Definition3.
insert code

Question 5

Based on the following table, what is the total float for activity (B)?

Correct Answer: C
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMP.v2026-10-28.q120 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.