The Health and Safety Training Project is closing as planned. According to the contract terms, suppliers must
submit all invoices within one week of project closure. The project manager will issue a project closure
notification informing all suppliers of this invoicing deadline as part of the 'recommended project closure'
activity.
Is this appropriate, and why?
Which of the following statements would NOT be included in the Project Product Description?
While capturing previous lessons, the Project Manager discovered several interesting facts about outsourcing.
Which fact is an appropriate lesson for the Outsourcing project?
During stage 4, a work package was authorized for the 'delivered pilot courses' to be completed by the end of week 2. The 'finalized materials' work package will start in week 3. Both work packages have zero tolerances, and finalizing the materials is dependent on feedback from the pilot courses.
During week 1, there were some problems with the pilot courses, so at the start of week 2 the team manager rescheduled the courses to week 3, and reported this in the weekly checkpoint report as the end of week 2.
Should the team manager have reported this delay previously as an issue, and why?