FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PRINCE2 Certification
  3. PRINCE2Foundation Exam
  4. PRINCE2.PRINCE2Foundation.v2026-10-10.q234 Dumps
  • ««
  • «
  • …
  • 39
  • 40
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47
  • 48
Download Now

Question 231

Which is a purpose of the Initiating a Project process?

Correct Answer: A
insert code

Question 232

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

Correct Answer: D
In PRINCE2, the project baseline should be updated when a change has been formally approved by the change authority. This is because the baseline represents the agreed standards and plan against which the project's performance is measured. Updating the baseline after the approval of changes ensures that the project documentation accurately reflects the current scope, timescales, and resource allocations, which are essential for tracking progress and managing by exception effectively.
(PRINCE2 7 Foundation Handbook, AXELOS)
insert code

Question 233

Which is part of quality control?

Correct Answer: A
Section: Volume B
Explanation
insert code

Question 234

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

Correct Answer: D
The purpose of the 'Identify the Risks' step within the recommended risk management procedure is to identify uncertainties that may impact the achievement of project objectives. This step involves recognizing potential issues and challenges that could threaten the project's success, enabling proactive management and mitigation strategies. References: PRINCE2 7 Foundation Handbook and official training materials.
insert code
  • ««
  • «
  • …
  • 39
  • 40
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47
  • 48
[×]

Download PDF File

Enter your email address to download PRINCE2.PRINCE2Foundation.v2026-10-10.q234 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.