How does the system derive the company code when you post a goods movement in a plant
Your company will procure finished goods from a supplier. The supplier will manufacture the product using components shipped from your company. Which process would you use for this scenario?
Please choose the correct answer.
For which of the following scenarios could you implement a stock determination strategy for a material in inventory management?
There are 3 correct answers to this question.
Response:
Which of the following occurs when you park a supplier invoice related to a purchase order ? Note : 2 correct answers
You procure some materials exclusively by consignment, you want MRP to create consignment purchase requisitions assigned to a supplier instead of normal purchase requisitions for these materials? Note : There are
2 correct answers to this question