You want to use automatic PR INTO PO for some raw materials
What are the prerequisites
Note : There are 3 correct answers to this question
Your MRP planning run detects a shortage of 2000 pieces of a certain material for which a quota arrangement is active. Each of your two vendors can supply only 1000 pieces at once.
What must you maintain to get a procurement proposal for 1000 pieces for each supplier?
There are 2 correct answers to this question.
Response:
What are some key features of the goods-receipt-based (GR-based) invoice verification?
There are 3 correct answers to this question.
Response:
Where do posting with automatic account determination occur in SAP Materials Management? Please choose the correct answer.
You want to manually post an initial entry of stock for a material in SAP S/4HANA. You should be able to enter both a quantity and an amount. How do you proceed?
Note: There are 2 correct answers to this question.