FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. SAP Certification
  3. C_TS422_2022 Exam
  4. SAP.C_TS422_2022.v2024-10-21.q53 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 16

How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,

Correct Answer: A,B
You can limit the validity of a BOM by plant and by period. The plant determines the organizational area of validity for the BOM, and you can assign the same BOM to different or further plants if the prerequisites are met. The period of validity for a BOM is restricted by the valid-from date and the valid-to date in the BOM header and item, which determine when the BOM becomes effective and when it ends. References: Validity of Bills of Material, BOM Item Validity
insert code

Question 17

You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

Correct Answer: A
Planning with final assembly (40) is a planning strategy that supports the consumption of planned independent requirements for the semi-finished material. This strategy is usedwhen the production of the finished product is triggered by the sales order, but the production of the semi-finished product is not. The semi-finished product is produced in advance based on the forecast and stored in stock. When the sales order is received, the planned independent requirements for the finished product are reduced by the sales order quantity, and the planned independent requirements for the semi-finished product are reduced by the corresponding component quantity. This way, the semi-finished product is consumed by the sales order and the production order for the finished product only requires the assembly of the components. This strategy allows for a shorter lead time and a higher flexibility for the finished product, while reducing the risk of excess stock for the semi-finished product. References: Planning with Final Assembly | SAP Help Portal, Planning Strategies | SAP Help Portal, SAP S/4HANA Production Planning and Manufacturing Certification Guide, page 53-54
insert code

Question 18

where does the system check master data selection settings during the creation of planned orders and production orders?
Note: There are 3 Correct answers to this question.

Correct Answer: A,D,E
The system checks the master data selection settings during the creation of planned orders and production orders in the following places:
In the bill of material (BOM), the system checks the selection ID, which determines which alternative BOM is selected for the material. The selection ID can be maintained in the material master or in the production version.
In the routing, the system checks the selection ID, which determines which alternative routing is selected for the material. The selection ID can be maintained in the material master or in the production version.
In the production version, the system checks the validity period, the lot size, and the selection profile, which determine whether the production version is valid and applicable for the material. The production version combines the BOM and the routing for a material and can be maintained in the material master or in the production version master data. References: SAP S/4HANA Manufacturing for Planning & Scheduling - Implementation Guide, page 16; [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 75.
insert code

Question 19

Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Correct Answer: B
You can achieve planning only for specific resources in Advanced Planning (PP/DS) by using a resource group. A resource group is a collection of resources that share the same characteristics and can be used interchangeably for production. You can assign a resource group to a product or a production version, and then use the resource group as a selection criterion in the planning board or the product view. This way, you can restrict the planning to only those resources that belong to the resource group. References: SAP S/4HANA Manufacturing for Planning & Scheduling - Implementation Guide, page 25; [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 79.
insert code

Question 20

You are trying to create a production order and NO valid production version can be selected. What could be the reasons?
Note: There are 2 correct answers to this question.

Correct Answer: C,D
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download SAP.C_TS422_2022.v2024-10-21.q53 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2025 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.