You want to schedule an operation finitely, without removing other operations. Which scheduling strategy do you select?
Correct Answer: D
The Find Slot scheduling strategy allows you to schedule an operation finitely, without removing other operations. It searches for a free slot in the resource's capacity that can accommodate the operation's duration and constraints. If no suitable slot is found, the operation is scheduled at the end of the resource's capacity. This strategy is useful for inserting urgent orders or operations into an existing schedule without disrupting it too much12 References: SAP S/4HANA Manufacturing for planning and scheduling - SAP Community SAP S/4HANA Manufacturing for Planning & Scheduling - Implementation Guide
Question 27
You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched, how does the insertion take place?
Correct Answer: B
The graphical planning table is a tool for capacity planning and scheduling that displays the operations and the work centers in a time-oriented view. You can use the graphical planning table to create, change, or dispatch operations manually or automatically. The planning direction determines whether the operations are scheduled from the start date or the finish date of the order. If the planning direction is forward, the operations are scheduled from the start date of the order1. If you want to insert an operation at a certain time on a work center in the graphical planning table, and the planning direction is forward, and the desired dispatching time coincides with an operation that has previously been dispatched, the insertion takes place as follows: The new operation is inserted at the desired time; the previously dispatched operation is moved backward (B): This is the correct answer. The system inserts the new operation at the specified time and shifts the previously dispatched operation to a later time, so that the sequence and the capacity requirements of the operations are maintained. The system also adjusts the start and finish dates of the order and the subsequent operations accordingly2. The other options are not correct for the following reasons: The new operation is inserted at the desired time; the previous dispatched operation is moved forward (A): This is not correct. The system does not move the previously dispatched operation to an earlier time, as this would violate the planning direction and the capacity constraints of the work center. The system only moves the previously dispatched operation to a later time, as explained in option B. The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation : This is not correct. The system does not insert the new operation after the previously dispatched operation, as this would not match the desired dispatching time specified by the user. The system inserts the new operation at the desired time and moves the previously dispatched operation backward, as explained in option B. The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation (D): This is not correct. The system does not insert the new operation before the previously dispatched operation, as this would violate the planning direction and the capacity constraints of the work center. The system inserts the new operation at the desired time and moves the previously dispatched operation backward, as explained in option B. References:
Question 28
How can you characterize dependent requirements in material requirements planning? Note: There are 2 correct answers to this question.
Correct Answer: B,C
Dependent requirements are the requirements for components that are derived from the requirements for the finished product or assembly. They are created when an independent requirement is created for the finished product or assembly, such as a planned independent requirement, a sales order, or a stock transport order. They are also created on assembly level during the planning run, when the system explodes the bill of material (BOM) of the finished product or assembly and calculates the requirements for the components based on the BOM structure and quantity. Dependent requirements can be created for multilevel or single-level BOM structures, depending on the planning strategy and the BOM explosion level. References: Dependent Requirements | SAP Help Portal, Material Requirements Planning (PP-MRP) | SAP Help Portal.
Question 29
Your project team decided to use a make-to-order planning strategy material in discrete manufacturing. what is the impact of this decision? Note: there are 2 correct answers to this question
Correct Answer: C,D,E
Question 30
How can you support a GMP (Good Manufacturing Practice)-compliant production process? Note: There are 3 correct answers to this question.