At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of "Done".
What two things should happen with the undone Product Backlog item? (Choose the best two answers.)
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:
The IT manager asks a Development Team for a status report describing the progress throughout the Sprint.
The Development Team asks the Scrum Master for advice. The Scrum Master should:
(Choose the best answer.)