FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. Scrum Certification
  3. PSM-I Exam
  4. Scrum.PSM-I.v2026-09-19.q335 Dumps
  • ««
  • «
  • …
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47
  • 48
  • 49
  • 50
  • …
  • »
  • »»
Download Now

Question 221

Who is responsible for crafting the Sprint Goal at the Sprint Planning?

Correct Answer: C
insert code

Question 222

Which three purposes does the definition of "Done" serve? (Choose the best three answers.)

Correct Answer: A,C,E
insert code

Question 223

Multiple Scrum Teams working on the same project must have the same Sprint start date.

Correct Answer: B
The correct answer is B, because multiple Scrum Teams working on the same project do not have to have the same Sprint start date. The Scrum Guide states that "multiple Scrum Teams often work together on the same product. One product goal unites them. Therefore, they must mutually define and comply with a definition of 'Done' that applies to their combined work product." Therefore, the synchronization of multiple Scrum Teams is based on their shared product goal and definition of 'Done', not on their Sprint start date.
insert code

Question 224

Which of the following is a Developer accountable for? (Choose the best two answers.)

Correct Answer: C,D
A Developer is accountable for creating a plan for the Sprint, the Sprint Backlog, and organizing the work required to meet the Sprint Goal, as stated in the Scrum Guide: "Developers are the people in the Scrum Team that are committed to creating any aspect of a usable Increment each Sprint. The specific skills needed by the Developers are often broad and will vary with the domain of work. However, the Developers are always accountable for:
Creating a plan for the Sprint, the Sprint Backlog;
Instilling quality by adhering to a Definition of Done;
Adapting their plan each day toward the Sprint Goal; and,
Holding each other accountable as professionals."
insert code

Question 225

What are the Scrum Artifacts? Select all applicable items.

Correct Answer: B,C,D
insert code
  • ««
  • «
  • …
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47
  • 48
  • 49
  • 50
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download Scrum.PSM-I.v2026-09-19.q335 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.