FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. Scrum Certification
  3. PSM-I Exam
  4. Scrum.PSM-I.v2026-09-19.q335 Dumps
  • ««
  • «
  • …
  • 38
  • 39
  • 40
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47
  • …
  • »
  • »»
Download Now

Question 206

(Which of the following are the Developers accountable for?
Choose the best two answers.)

Correct Answer: B,C
The correct answers are B and C. According to the Scrum Guide, the Developers are accountable for creating a plan for the Sprint, which is the Sprint Backlog. That makes Option C correct. They are also accountable for organizing the work required to meet the Sprint Goal, which makes Option B correct. These are core elements of self-management in Scrum. Developers decide how to turn selected Product Backlog items into a valuable, usable Increment and how to adapt their plan throughout the Sprint.
Option A is incorrect because Scrum does not define "reporting productivity" as a Developer accountability.
Scrum focuses on outcomes, transparency, and progress toward the Sprint Goal rather than traditional productivity reporting. Option D is incorrect because selecting the Product Owner is not a Developer accountability. Role assignments are determined by the organization, not by the Developers.
These accountabilities matter because Scrum relies on Developers to manage their own work rather than wait for direction from others. By creating and adapting the Sprint Backlog and organizing work toward the Sprint Goal, the Developers enable collaboration, flexibility, and accountability for producing a Done Increment each Sprint.
insert code

Question 207

When is it most appropriate for a Development Team to change the definition of "Done"?

Correct Answer: D
insert code

Question 208

The IT manager asks a Development Team for a status report describing the progress throughout the Sprint.
The Development Team asks the Scrum Master for advice. The Scrum Master should:
(Choose the best answer.)

Correct Answer: A
The Scrum Master should talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review, as stated in [5]: "The Scrum Master should educate the IT manager about how Scrum works and how progress is measured. The Scrum Master should invite the IT manager to attend the Sprint Review where the Development Team demonstrates what was accomplished during the Sprint. The Scrum Master should also explain that status reports are not necessary in Scrum, as transparency is ensured by using artifacts such as Product Backlog, Sprint Backlog, and Increment."
insert code

Question 209

A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities.
Which two activities are part of the Product Owner role according to Scrum? (Choose two.)

Correct Answer: A,B
The Product Owner is responsible for ensuring that the most valuable functionality is produced first, at all times, by ordering and prioritizing the Product Backlog. The Product Owner also interacts with stakeholders to understand their needs and expectations, and to communicate the vision and progress of the product. The other options are not part of the Product Owner role according to Scrum, as they are either too prescriptive or too technical.
insert code

Question 210

What is the best suited structure for Development Teams in order to produce integrated Increments?

Correct Answer: B
According to the Scrum Guide, an Increment is a concrete stepping stone toward the Product Goal. Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together. In order to provide value, an Increment must be usable. Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint Review thus supporting empiricism. However, an Increment may be delivered to stakeholders prior to the end of the Sprint. The Sprint Review should never be considered a gate to releasing value. Therefore, in order to produce integrated Increments that are potentially releasable, the best suited structure for Development Teams is to develop functionality from beginning to end throughout all technical layers.
insert code
  • ««
  • «
  • …
  • 38
  • 39
  • 40
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download Scrum.PSM-I.v2026-09-19.q335 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.