FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. Scrum Certification
  3. PSPO-I Exam
  4. Scrum.PSPO-I.v2024-10-03.q180 Dumps
  • ««
  • «
  • …
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • …
  • »
  • »»
Download Now

Question 126

What happens if the Scrum Team cannot complete its work by the end of the Sprint?
(choose the best answer)

Correct Answer: A
Explanation
If the Scrum Team cannot complete its work by the end of the Sprint, the Sprint does not get extended.
Instead, the unfinished Sprint Backlog Items go back to the Product Backlog and can be addressed in the following Sprint12. This approach allows the team to get better at estimating and reduces complexity due to the consistency of the Scrum Events2. The Scrum Team continuously learns and adapts12.
insert code

Question 127

The Scrum Master can decide which Scrum Events are required in the Scrum project.

Correct Answer: A
insert code

Question 128

Who determines how work is performed during the Sprint?
(choose the best answer)

Correct Answer: D
The Developers are the people in the Scrum Team who are committed to creating any aspect of a usable Increment each Sprint. The Developers are accountable for organizing and managing their work. Only the Developers can decide how to perform the work during the Sprint1. The Developers plan the work necessary to create an Increment that meets the Definition of Done during the Sprint Planning event. This is often done by decomposing Product Backlog items into smaller work items of one day or less. How this is done is at the sole discretion of the Developers2. The Developers also inspect their progress toward the Sprint Goal and adapt their plan during the Daily Scrum1. The Developers are self-managing, which means they decide internally who does what, when, and how1. The Scrum Master, the Product Owner, the team manager, and the subject matter experts are not involved in determining how the work is performed during the Sprint. They may provide guidance, feedback, or support, but they do not interfere with the Developers' autonomy and accountability134. Reference:
Scrum Guide
What is a Developer?
Who Determines How Work Is Performed During The Sprint?
What is Sprint Planning?
insert code

Question 129

What are the 3 Pillars of Scrum?

Correct Answer: C,D,E
insert code

Question 130

Select typical responsibilities of a Scrum Master to serve the organization.

Correct Answer: A,B,C
insert code
  • ««
  • «
  • …
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download Scrum.PSPO-I.v2024-10-03.q180 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.