Why are Sprints fixed length events of one month or less?
Correct Answer: C
Question 147
The Sprint Review is an opportunity for inspecting and adapting in Scrum?
Correct Answer: A
Question 148
Who does the work to make sure Product Backlog items conform to the Definition of Done? (choose the best answer)
Correct Answer: D
Explanation The work to make sure Product Backlog items conform to the Definition of Done is done by the Developers. This is because: * The Developers are accountable for creating a "Done" Increment in every Sprint. They must ensure that every Product Backlog item they work on meets the Definition of Done before it is considered complete. * The Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product. It is a shared understanding among the Scrum Team and the stakeholders of what "Done" means for any Product Backlog item that is selected for a Sprint. * The Developers are self-managing professionals who organize and manage their own work. They decide how to best accomplish their work, rather than being directed by others outside the Scrum Team. Other options, such as the Product Owner, the Quality Assurance Team, the Scrum Team, or the Scrum Master, are not responsible for making sure Product Backlog items conform to the Definition of Done. They may have different roles and accountabilities in Scrum, but they do not do the actual work of creating a "Done" Increment. References: * [Scrum Guide], page 7, section "Developers" * [Scrum Guide], page 10, section "Definition of Done" * [Scrum Guide], page 7, section "The Scrum Team"
Question 149
Which of the following are true about the Product Owner? (choose the best two answers)
Correct Answer: A,D
* The Product Owner is one person, not a committee or a team of people. The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team. The * Product Owner is responsible for managing and refining the Product Backlog, collaborating with the stakeholders and the Developers, and ordering the items in a way that best achieves goals and missions. The Product Owner represents the interests of everyone with a stake in the product and ensures that the Scrum Team works on the right things at the right time. * Having multiple Product Owners for one product would create conflicts, overlaps, gaps, and inefficiencies. It would also make it harder to maintain a clear and consistent product vision, strategy, roadmap, and backlog. Therefore, the Scrum Team can not have multiple Product Owners. * The Product Owner is accountable for ordering the Product Backlog. The Product Backlog is an ordered list of everything that is known to be needed in the product. It is the single source of truth for the Scrum Team and the stakeholders. It contains all the requirements, features, functions, enhancements, fixes, and anything else that can deliver value to the customers and users of the product. The Product Owner orders the items in the Product Backlog based on factors such as value, risk, priority, dependency, feedback, or market conditions. References: * Scrum Guide: https://www.scrumguides.org/scrum-guide.html * Product Owner: https://www.scrum.org/resources/what-is-a-product-owner * Product Backlog: https://www.scrum.org/resources/what-is-a-product-backlog
Question 150
Which of the following describes best the Sprint Review?