FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. APICS Certification
  3. CPIM-8.0 Exam
  4. APICS.CPIM-8.0.v2026-02-13.q305 Dumps
  • ««
  • «
  • …
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • …
  • »
  • »»
Download Now

Question 101

An organization needs a firewall that maps packets to connections and uses Transmission Control Protocol/Internet Protocol (TCP/IP) header fields to keep track of connections. Which type of firewall will be recommended?

Correct Answer: C
insert code

Question 102

An organization is preparing for a natural disaster, and management is creating a Disaster Recovery Plan (DRP). What is the BEST input for prioritizing the restoration of vital Information Technology (IT) services?

Correct Answer: D
insert code

Question 103

An organization is considering options to outsource their Information Technology (IT) operations. Although they do not sell anything on the Internet, they have a strong requirement in uptime of their application. After the offerings received by the Cloud Service Provider (CSP), the IT manager decided it was mandatory to develop processes to continue operations without access to community or public cloud-based applications. Which of the following arguments MOST likely led the IT manager to make this decision?

Correct Answer: B
insert code

Question 104

A manufacturer has a forecasted annual demand of 1,000,000 units for a new product. They have to choose 1 of 4 new pieces of equipment to produce this product. Assume that revenue will be $10 per unit for all 4 options.
Which machine will maximize their profit if the manufacturer anticipates market demand will be steady for 3 years and there is no residual value for any of the equipment choices?
MachineFixed CostVariable Cost per UnitAnnual Capacity
AS100.000$6 00800,000 units
B$200,000$5 501.000,000 units
C$250,000$5 001,200,000 units
D$1 000.000$4 501 400.000 units

Correct Answer: C
To maximize profit, the manufacturer should choose the machine that has the lowest total cost per unit of demand. The total cost per unit of demand is calculated by adding the fixed cost per unit of demand and the variable cost per unit. The fixed cost per unit of demand is obtained by dividing the fixed cost by the annual demand. The variable cost per unit is given in the table. The total cost per unit of demand for each machine is:
Machine A: 1,000,000100,000+6.00=6.10
Machine B: 1,000,000200,000+5.50=5.70
Machine C: 1,000,000250,000+5.00=5.25
Machine D: 1,000,0001,000,000+4.50=5.50
The lowest total cost per unit of demand is for Machine C, which is $5.25. Therefore, Machine C will maximize the profit for the manufacturer.
References:
Some possible references for this question are:
CPIM Part 1 Exam Content Manual, Version 8.0, Domain 3: Plan and Manage Supply, Section A: Plan and Manage Supply Chain Capacity, Topic 2: Capacity Planning Concepts, Subtopic b: Capacity planning methods, Page 30 CPIM Part 1 Learning System, Version 8.0, Module 3: Plan and Manage Supply, Section 3.2: Capacity Planning Concepts, Topic 3.2.2: Capacity Planning Methods, Subtopic 3.2.2.2: Cost-Volume Analysis, Pages 3-24 to 3-26 CPIM Part 1 Study Guide, Version 8.0, Module 3: Plan and Manage Supply, Section 3.2: Capacity Planning Concepts, Topic 3.2.2: Capacity Planning Methods, Subtopic 3.2.2.2: Cost-Volume Analysis, Pages 3-24 to 3-26
insert code

Question 105

In a make-to-stock (MTS) environment, the master production schedule (MPS) Is usually a schedule of which of the following types of items?

Correct Answer: B
In a make-to-stock (MTS) environment, the master production schedule (MPS) is usually a schedule of finished goods items that are ready to be sold to customers. Phantom items, component/subassembly items, and raw material items are not typically scheduled in the MPS, but rather in the material requirements planning (MRP) system, which is driven by the MPS. References:
CPIM 8.0 Exam Content Manual Preview, page 10, section 4.1.1
CPIM Part 1 Study Guide, page 66, section 4.1.1
CPIM Part 1 Learning System, Module 4, Lesson 1, Topic 1: Master Production Schedule
insert code
  • ««
  • «
  • …
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download APICS.CPIM-8.0.v2026-02-13.q305 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.