Which of the following BEST describes the purpose of black hat testing during an assessment?
Correct Answer: D
Question 142
A plant uses a level production strategy due to the high costs of hiring and letting go of skilled employees. The constrained resource is due to be upgraded in the fourth month of the planning horizon, and that will reduce capacity for that month by 17%. Which of the following actions would be appropriate in this situation to maintain current levels of customer service and gross margin?
Correct Answer: A
A level production strategy is a manufacturing strategy where a company produces a fixed number of products at a fixed rate1. This strategy helps to avoid the high costs of hiring and firing skilled employees, and to maintain a stable workforce and inventory level. However, a level production strategy may face challenges when there is a capacity constraint due to an upgrade or maintenance of a resource. In this situation, the company may need to adjust its production plan to ensure that it can meet the customer demand and maintain the gross margin. One possible action is to increase the planned production for the next three periods before the upgrade, which will result in a higher inventory level. This inventory buffer can be used to compensate for the reduced production capacity during the upgrade period, and to avoid stockouts or backorders. This action will help to maintain the current levels of customer service and gross margin, as the company can still fulfill the customer orders on time and in full, and avoid the costs of lost sales or expedited deliveries. Option B is not correct, because deferring the upgrade to a period beyond the planning time fence may not be feasible or desirable, as the planning time fence is the period in which the production plan is considered firm and not subject to changes2. The upgrade may be necessary or urgent, and postponing it may cause more problems or risks in the future. Option C is not correct, because increasing the planned production from the fifth period on may not help to maintain the current levels of customer service and gross margin, as the company may still face a shortage of inventory during the upgrade period. Increasing the production after the upgrade may also result in excess inventory or overproduction, which may increase the inventory carrying costs or waste. Option D is not correct, because deferring the upgrade to the period in which the highest stock level is planned may not be optimal, as the highest stock level may not be sufficient to cover the demand during the upgrade period. Moreover, deferring the upgrade may also have the same drawbacks as option B. Reference: 1 Guide to Level Production Strategy - Welp Magazine 3 2 Planning Time Fence | SAP Help Portal 4
Question 143
Following the go-live of a new financial software, an organization allowed the Information Technology (IT) officer to maintain all rights and access permissions to help the organization staff should they have challenges in their day-to-day work. What is the BEST way to categorize the situation?
Correct Answer: A
Question 144
Which of the following methods places a replenishment order when the quantity on hand falls below a predetermined level?
Correct Answer: B
Fixed order quantity is a method that places a replenishment order when the quantity on hand falls below a predetermined level, called the reorder point. The reorder point is calculated based on the expected demand during the lead time and the safety stock. The order quantity is fixed and constant, and it is determined by the economic order quantity (EOQ) formula or other criteria. Fixed order quantity is also known as the order point /order quantity (OP/OQ) system or the continuous review system. Option A is not correct, because min-max system is a method that places a replenishment order when the quantity on hand falls below a minimum level, called the order point. The order quantity is variable and depends on the difference between the maximum level and the current inventory level. Min-max system is also known as the two-bin system or the bin system. Option C is not correct, because periodic review is a method that places a replenishment order at fixed intervals of time, regardless of the quantity on hand. The order quantity is variable and depends on the difference between the target inventory level and the current inventory level. Periodic review is also known as the fixed order interval (FOI) system or the periodic order quantity (POQ) system. Option D is not correct, because available-to-promise (ATP) is not a method of inventory replenishment, but a calculation of the uncommitted portion of the current inventory and planned production. ATP is used to promise delivery dates to customers based on the availability of inventory and production capacity. : Inventory Management and Control Inventory Replenishment Methods Inventory Replenishment Policies
Question 145
Check sheets can be used to:
Correct Answer: A
Check sheets are simple tools that allow data to be collected and recorded in an organized manner. Check sheets can be used to determine the frequency of a defect and the timeperiod between occurrences by counting and categorizing the number of defects that occur over a specified time interval. Check sheets can also help to identify the causes and patterns of defects, and to monitor the effectiveness of improvement actions. The other statements are not true about check sheets. Check sheets do not provide a quick method to identify if possible defects exist, as they require data collection and analysis. Check sheets do not allow improvement teams to see if action items are being completed on time, as they are not designed to track the progress of tasks. Check sheets do not provide an indication of correlation between defects, as they do not measure the relationship between variables. References: Check Sheet | APICS Dictionary Term of the Day, APICS CPIM 8 Planning and Inventory Management | ASCM