FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. EXIN Certification
  3. CDCS Exam
  4. EXIN.CDCS.v2026-03-09.q52 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 11

What is a potential disadvantage of using water mist as a fire extinguishing system?

Correct Answer: B
A potential disadvantage of using a water mist fire suppression system is that it can rapidly increase the humidity within the data center, which may pose risks to sensitive electronic equipment. Excessive humidity can lead to condensation, which could damage electronics and lead to short circuits or corrosion over time.
Detailed Explanation:
Water mist systems use fine droplets to suppress fires by cooling and displacing heat. However, the moisture generated may raise the humidity level to the point where it exceeds safe operational limits for IT equipment. Therefore, while water mist systems are effective in fire suppression, they may not be ideal in environments where high humidity could damage sensitive equipment.
EPI Data Center Specialist References:
EPI guidelines advise considering the impact of humidity from fire suppression systems, particularly in environments housing electronic equipment. It's essential to weigh the benefits of fire suppression against potential risks to operational equipment when choosing suppression methods.
insert code

Question 12

What is the advantage or disadvantage of using MPO (Multi-fiber Push On)/pre-terminated fiber?

Correct Answer: C
MPO (Multi-fiber Push On) pre-terminated fiber offers the advantage of quick installation and supports high- speed upgrades up to 40 Gbit/s and 100 Gbit/s. This technology simplifies connections by allowing multiple fibers to be connected in a single plug-and-play module, reducing installation time and making future expansions or upgrades to higher speeds easier.
Detailed Explanation:
MPO connectors consolidate multiple fiber connections into a single interface, which simplifies cable management and reduces installation complexity. This setup is particularly beneficial in data centers where high-speed networks are essential, and where rapid deployment is necessary. MPO pre-terminated fiber also supports the use of OM4 fiber, making it compatible with existing high-performance cabling infrastructure.
EPI Data Center Specialist References:
EPI training highlights that pre-terminated fiber solutions, like MPO, can greatly enhance efficiency in data centers. By reducing installation time and providing scalability for higher transmission speeds, they align with best practices for maintaining flexible and future-ready network infrastructure.
insert code

Question 13

How is the PUE ratio calculated?

Correct Answer: A
PUE (Power Usage Effectiveness) is the most widely used metric to evaluate the energy efficiency of data centers. Defined by The Green Grid and adopted in ISO/IEC 30134-2, PUE is the ratio of the total facility power to the ICT (IT load) power.
Formula:
* Total Facility Power includes all electrical consumption: IT, cooling, lighting, power distribution losses, UPS inefficiency, etc.
* ICT Equipment Power is only the load drawn by servers, storage, and networking gear.
An ideal PUE is 1.0, meaning all power is used by ICT equipment with no overhead. Typical enterprise values are 1.5-2.0, while hyperscale operators target <1.2.
Other options are incorrect:
* B represents the inverse metric, known as DCiE (Data Center infrastructure Efficiency).
* C and D are partial subsystem efficiency metrics, not the global PUE.
References: ISO/IEC 30134-2 (KPIs - PUE), The Green Grid White Paper #49, ANSI/TIA-942-B §7.3.
insert code

Question 14

What should you consider when using raised floor tiles with air deflectors or louvers?

Correct Answer: A
Raised floor tiles with air deflectors or louvers are typically heavier than standard tiles due to the additional materials and mechanisms used to direct airflow. The added weight can pose challenges for installation and adjustment, and consideration must be given to the floor's load capacity and ease of maintenance.
Detailed Explanation:
Tiles with deflectors or louvers help direct airflow, enhancing cooling efficiency by focusing cool air where needed. However, these tiles are often heavier, which can affect handling and require reinforced raised floor systems. It's essential to factor in the weight for any floor tile replacements or installations to ensure they are compatible with the raised floor's structural capacity.
EPI Data Center Specialist References:
EPI data center design training mentions the potential impact of heavy tiles on floor handling and load capacity. Data center operators need to plan for safe handling and load-bearing capacity when using such specialized tiles.
insert code

Question 15

Should aerosol cleaning solutions be used in the computer room?

Correct Answer: B
Aerosol sprays release particulates and residues into the environment, which can contaminate sensitive ICT equipment. Such contamination accelerates corrosion, interferes with airflow, and increases particulate levels beyond ASHRAE recommended limits.
Proper cleaning should use HEPA-filtered vacuum systems or dry wipes, not aerosols. Even odor control aerosols are disallowed in critical rooms.
Therefore, aerosol cleaning solutions must never be used.
References: ASHRAE TC 9.9 "Contamination Guidelines," NFPA 75 §8.4.
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download EXIN.CDCS.v2026-03-09.q52 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.