FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. EXIN Certification
  3. CDCS Exam
  4. EXIN.CDCS.v2026-03-09.q52 Dumps
  • ««
  • «
  • …
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • …
  • »
  • »»
Download Now

Question 26

What should be implemented when an Inergen-based fire suppression system is installed in the computer room?

Correct Answer: C
Inert gas systems (Inergen, Argonite, Nitrogen) extinguish fires by reducing oxygen concentration through massive gas discharge. This rapid release causes a significant pressure rise inside the room. To avoid structural damage to walls, ceilings, or raised floors, pressure relief vents (pressure release valves) must be installed.
* A (drainage) applies to water suppression.
* B (tank location) is logistical but not mandatory; remote storage with piping is acceptable.
* D (water leak detection) is unrelated to inert gas suppression.
Therefore, the critical safety requirement is pressure relief.
References: NFPA 2001 §5.2.1.2 (Pressure Relief), ISO 14520-1 §5.2.
insert code

Question 27

Is it allowed to make design changes during the implementation phase?

Correct Answer: D
Design changes during the implementation phase are generally allowed only when there is a strong business and/or technical justification. Changes at this stage can lead to delays, increased costs, or compromise design integrity. Thus, a rigorous assessment is required to ensure any modifications are essential and provide clear benefits or address critical issues.
Detailed Explanation:
Changes post-design freeze should be minimized to avoid scope creep and additional costs. However, if a technical issue arises that would affect operational goals, or a business need warrants modification, justified changes are permissible, following an impact assessment and approval process.
EPI Data Center Specialist References:
EPI project management guidelines recommend a controlled change management process during implementation, allowing changes only when they align with critical objectives or address unforeseen issues that affect the project's success.
insert code

Question 28

You are working with a customer who requires a guarantee that THDi levels coming from the UPS should not exceed more than 3% THDi. Furthermore, he wants to run a power-efficient data center. The UPS has a 6- Pulse SCR/Thyristor based rectifier. The current load on the UPS is approximately 80%. The customer indicates they are not expecting any changes on the ICT infrastructure for the next 3 years.
What should you recommend?

Correct Answer: C
Given the customer's requirement to limit Total Harmonic Distortion (THDi) to below 3% and the presence of a 6-pulse SCR/Thyristor-based rectifier, an active harmonic filter is the best solution. A 6-pulse rectifier typically generates higher harmonic distortion, often exceeding 3%, especially under substantial loads like
80%. An active harmonic filter dynamically monitors and compensates for harmonic distortion, effectively reducing THDi and supporting a more power-efficient operation, aligning with the customer's energy efficiency goals.
Detailed Explanation:
Passive harmonic filters can reduce harmonics but are less effective at maintaining low THDi levels under varying loads. Active filters offer real-time correction and can achieve lower THDi levels than passive filters, especially in systems with fluctuating loads or where strict harmonic limits are required. Installing an active harmonic filter will ensure compliance with the specified THDi limits and optimize power quality.
EPI Data Center Specialist References:
EPI guidance on power quality management recommends active harmonic filters for environments where strict THDi levels are necessary. Active filters offer better control over harmonic levels, supporting both compliance and operational efficiency.
insert code

Question 29

A computer room needs to be fitted out with a gas-based fire suppression system. The computer room will be a high-density data center with about 30% of the racks being closed circuit cooling blade-center racks.
Should the supplier of the fire suppression system be informed on the design of the racks?

Correct Answer: C
The design and configuration of racks, particularly high-density and closed-circuit cooling racks, directly impact the fire suppression system design. Closed-circuit cooling racks, like blade-center racks, can affect airflow and potentially trap heat, influencing how fire suppression agents are distributed within the space.
Therefore, it is essential to inform the fire suppression system supplier about the rack design to ensure effective coverage and proper agent distribution.
Detailed Explanation:
High-density racks can change how smoke and heat travel, which in turn affects fire detection and suppression. Closed racks with built-in cooling can isolate airflow, requiring adjustments in fire suppression design to ensure that suppression agents reach all necessary areas, including within enclosed spaces. The supplier may need to account for these factors to ensure proper protection coverage.
EPI Data Center Specialist References:
The EPI Data Center Specialist training underscores that fire suppression systems must be tailored to the specific environmental characteristics of the data center. The design of racks, particularly high-density configurations, should always be considered to ensure that suppression agents can effectively control a fire, even in contained rack spaces.
insert code

Question 30

You have three UPS systems connected in parallel. The UPS systems have an imbalance in the load sharing of approximately 20%.
What should you recommend?

Correct Answer: A
An imbalance in load sharing between UPS systems connected in parallel can often result from unequal cable lengths to the common busbar. If the cabling from each UPS to the busbar varies significantly in length, it can lead to differences in impedance, resulting in uneven load distribution. Ensuring that cable lengths are consistent helps to balance the load sharing across the UPS systems.
Detailed Explanation:
Parallel UPS systems rely on uniform impedance to share loads evenly. Differences in cable lengths cause variations in resistance, leading to one or more UPS units carrying a disproportionate share of the load. Standardizing cable lengths ensures equal impedance, which promotes balanced load sharing and prevents one UPS from being overburdened, thus maintaining overall system reliability.
EPI Data Center Specialist References:
EPI guidelines recommend checking cable lengths when load imbalances occur in parallel UPS configurations. Ensuring equal lengths is a common method to resolve impedance issues that affect load distribution, which is critical for the stable operation of redundant power systems.
insert code
  • ««
  • «
  • …
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download EXIN.CDCS.v2026-03-09.q52 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.