FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. EXIN Certification
  3. CITM Exam
  4. EXIN.CITM.v2026-01-22.q18 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • »
Download Now

Question 6

What is the correct sequence of activities for a risk assessment?

Correct Answer: C
The correct sequence for arisk assessment, as perISO 31000andISO/IEC 27001, is:Establish context - identify - analyse - evaluate - treatment(C).
* Establish context:Define the scope, objectives, and criteria for the risk assessment (e.g., organizational goals, assets, and risk appetite).
* Identify:Identify potential risks (e.g., threats and vulnerabilities) that could impact objectives.
* Analyse:Assess the likelihood and impact of identified risks to determine their severity.
* Evaluate:Compare risks against risk criteria to prioritize them for treatment.
* Treatment:Implement controls or strategies to mitigate, avoid, transfer, or accept risks.
* Option A:Incorrect, as "monitor and review" is a post-treatment step, not the starting point.
* Option B:Incorrect, as "communication" is not a distinct step in risk assessment; it's embedded throughout.
* Option D:Incorrect, as it skips "establish context," which is essential for defining the assessment's scope.
This sequence ensures a structured, systematic approach to risk assessment, aligning with organizational objectives.
Reference:EPI CITM study guide, under Risk Management, likely references ISO 31000 or ISO/IEC 27001 for risk assessment processes. Check sections on risk assessment methodologies or risk management lifecycle.
insert code

Question 7

Your organization considers a job rotation program. What is the main objective?

Correct Answer: A
The main objective of ajob rotation programin anIT organizationis tosupport the long-term continuity of the organization(A). Job rotation ensures that multiple staff members are trained across various roles and tasks, reducing dependency on specific individuals and mitigating risks associated with staff turnover or absences. This approach enhances organizational resilience by creating a flexible, cross-trained workforce capable of maintaining operations, aligning withIT organizationprinciples for workforce planning and business continuity.
* Train staff on a range of activities (B):While training is a benefit, it is a means to achieve continuity, not the primary objective.
* Increase staff job satisfaction (C):Job satisfaction may be a secondary benefit, but it's not the main goal in an IT context.
* Allow staff a diversity in responsibilities (D):Diversity in tasks is a byproduct, not the primary focus, which is organizational continuity.
According tohuman resource managementframeworks, job rotation is a strategic tool for ensuring operational stability, particularly in IT environments where specialized skills are critical.
Reference:EPI CITM study guide, under IT Organization, likely discusses workforce planning and job rotation for continuity. Check sections on human resource management or organizational resilience.
insert code

Question 8

Activities in a project are discussed in a Work Breakdown Structure (WBS) session during the planning phase. Team members inform the project manager that whilst estimating the duration for activities, a lot of data exist about the effort required for each of them. Which estimation technique is best considered?

Correct Answer: D
When a lot of data exist about the effort required for project activities, thebottom-upestimation technique (D) is most appropriate. This method involves estimating the effort for each task in theWork Breakdown Structure (WBS)individually, then aggregating them to derive the total project duration or cost. It leverages detailed data for accuracy, as perPMBOK's estimation techniques.
* Top-down (A):Uses high-level estimates based on historical data or expert judgment, less accurate with detailed task data available.
* Three-point (B):Uses optimistic, pessimistic, and most likely estimates for uncertainty, but is less focused on leveraging detailed effort data.
* Comparative (C):Likely refers to analogous estimation, which relies on comparisons to past projects, not detailed task data.
Bottom-up estimation is ideal when detailed effort data is available, ensuring precision in project planning.
Reference:EPI CITM study guide, under Project Management, likely covers PMBOK's estimation techniques, emphasizing bottom-up for detailed data scenarios. Refer to sections on project planning or cost
/duration estimation.
insert code

Question 9

The introduction of a security awareness program has resulted in a quick decrease in security incidents. Eight months later, security incidents are showing a sudden increase, and the blame is put on a non-functioning security awareness program. What is most likely the cause?

Correct Answer: C
Security awareness programs require ongoing engagement to remain effective. If security incidents decrease initially but increase after eight months, the most likely cause is thatmessage materials are few and static, and renewal is not taking place(C). Static content becomes outdated or ignored over time, reducing its impact. Regular updates, new campaigns, and varied delivery methods (e.g., videos, quizzes) are essential to maintain employee awareness and adapt to evolving threats, as perISO/IEC 27001orNISTsecurity awareness guidelines.
* Insufficient budget (A):While budget constraints could limit program scope, there's no evidence in the scenario to suggest this is the primary issue.
* Scope too narrow (B):A narrow scope might limit effectiveness initially, but the initial success suggests the scope was adequate; the issue is sustaining engagement.
* Lack of resources for instructor-led sessions (D):Instructor-led sessions are one delivery method, but the core issue is likely outdated content rather than delivery format.
Reference:EPI CITM study guide, under Information Security Management, likely discusses security awareness program maintenance, emphasizing the need for regular content updates. Refer to sections on security awareness or human factors in security.
insert code

Question 10

Before the marketing department will decide on a new advertising campaign, it wants to be able to gain more insights into the customer, being able to predict the products customers will purchase in the near future. What is a 'must-have' criterion in terms of the technology the marketing department is interested in?

Correct Answer: B
To predict future customer purchases, the marketing department requiresadvanced analytics(B), which involves sophisticated data analysis techniques, such as predictive modeling, machine learning, and data mining. These technologies enable the department to analyze customer behavior, identify patterns, and forecast purchasing trends, supporting targeted advertising campaigns.
* Records Management System (RMS) (A):Focuses on managing and storing records, not predictive analysis.
* Ad hoc analysis (C):Allows for on-demand, one-off queries but lacks the predictive capabilities of advanced analytics.
* Business Intelligence (BI) (D):Provides reporting and historical data analysis but is less focused on predictive modeling compared to advanced analytics.
Advanced analytics aligns withIT strategygoals of leveraging data for competitive advantage, as it supports predictive insights critical for marketing decisions.
Reference:EPI CITM study guide, under IT Strategy, likely discusses data-driven technologies like advanced analytics for business decision-making. Refer to sections on emerging technologies or data analytics.
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • »
[×]

Download PDF File

Enter your email address to download EXIN.CITM.v2026-01-22.q18 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.