To keep costs at a minimum and decrease the completion time by 1-1/2 days, Networks, Inc. should crash activity)
Correct Answer: A
The critical longest) path is A-D-E, which has an expected time of 13 days 5.5 +7.5). However, to decrease the project's completion time by 1.5 days, paths A-B-C-E 4.5 + 1.0 + 6.5 = 12 days) and A-B-D-E 4.5 + .5 + 7.5 = 12.5 days) as well as A-D-E must also be shortened. Hence, A-D-E must be reduced by 1.5 days, A-B-C-E by .5 day, and A-B-D-E by 1.0 day. The only way to decrease A-D-E by 1.5 days is to crash activity. AD 5.5 expected time -4.0 crash time = 1.5 days). Crashing DE results in a 1.0-day saving 7.5 - 6.5) only. Crashing AB is the efficient way to reduce both A-B-C-E and A-B-D-E by the desired amount of time because it i s hart of both paths. The incremental cost of crashing AB is U $1,000 US $4,000 crash cost - US $3,000 normal cost) to shorten the completion time by 1.0 day 4.5 - 3.5). The alternatives for decreasing both A-B-C-E and A-B-D-E are more costly.
Question 242
Various tools are employed to control large scale projects. They include all of the following except:
Correct Answer: C
Statistical process quality) control is not used to control large scale projects. Statistical quality control is a method of determining whether the shipment or production run of units lies within acceptable limits. It is also used to determine whether production processes are out of control.
Question 243
Which of the following statements regarding database management systems is not correct?
Correct Answer: A
Question 244
Which of the following is not a common feature of cumulative preferred stock?
Correct Answer: D
Question 245
Which of the following statements is true regarding outsourced business processes?