Harold is the project manager of a large project in his organization. He has been actively communicating and working with the project stakeholders. One of the outputs of the manage stakeholder expectations process can actually create new risk events for Harold's project. Which output of the manage stakeholder expectations process can create risks?
You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response?
Which of the following is the PRIMARY purpose of an effective set of key risk indicators (KRIs)?
Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?
Due to continually missed service level agreements (SLAs), an enterprise plans to terminate its contract with a vendor providing IT help desk services. The enterprise s IT department will assume the help desk-related responsibilities. Which of the following would BEST facilitate this transition?